Since we have failed the 2.2M1 release date I propose the following new 
schedule:

Original dates:

* 2.2M1: 28 Dec 2009
* 2.2M2: 18 Jan 2010
* 2.2RC1: 1st Feb 2010
* 2.2 RC2/Finale: 8 Feb 2010

New dates:

* 2.2M1: 11th of Jan (or 12th of Jan since Jean-Vincent is almost ready to 
include the new profile UI + new watchlist UI and he may need one day more)
* 2.2M2: 25th of Jan (one week more, i.e. 2 weeks in total - That's ok since 
we've almost done all planned stuff in 2.2M1 - see 
http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap)
* 2.2RC1: 1st Feb 
* 2.2 RC2/Finale: 8 Feb

Here's my +1