On Fri, Jan 20, 2012 at 18:28, Marius Dumitru Florea <
[email protected]> wrote:

> Hi devs,
>
> The 3.4 final release has been delayed almost 3 weeks, for various
> reasons, so we need to adjust the planning for 3.5. I propose:
>
> 3.4Final: 23 January (this Monday, so in 3 days)
> 3.5RC1: 6 February (2 weeks)
> 3.5Final: 13 February (1 week)
>
> WDYT?
>

+1 - only remark that on 4-5 February is FOSDEM and some people may have
holidays in that period - but maybe will not impact the release

Thanks,
Caty


>
> I can be the release manager of 3.5 but we need a release manager for
> the beginning of the 4.x cycle.
>
> Thanks,
> Marius