Hi devs, In a previous mail I proposed the following dates for 3.5:
3.5RC1: 6 February (2 weeks) 3.5Final: 13 February (1 week) As you can see I haven't included a milestone because the initial plan was to do only bug fixes as 3.5 is the last release of the 3.x cycle. It seems though that we're going to introduce new stuff and improvements (for Extension Manager and App Within Minutes at least) and thus a milestone is now needed. Thus I propose these new dates: 3.5M1: 6 February (2 weeks) 3.5RC1: 13 February (1 week) 3.5Final: 20 February (1 week) WDYT? Thanks, Marius _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs