After some discussion on IRC, the current plan for releasing 4.1-rc-1 and 4.1 
has been determined
to be unworkable. The specific part at issue is the calling of a VOTE to 
release what is currently
in the staging repository and waiting 72 hours for it to be verified. While 
this provides the best
quality assurance, each blocker means another failed vote and another 72 hours 
+ the time to fix
the issue and stage another release.

Proposal:
Stage the release 2 days before the official release date allowing blockers to 
be found and fixed.
Fix the issues and release the resulting build without any guaranteed testing 
window, hoping that
the patches to the earlier issues didn't introduce any regressions.

I don't like it much but it seems that it sucks less than all of the 
alternatives so +0 for me.

Caleb