+1

Thanks,
Eduard

On Wed, Sep 12, 2012 at 12:56 PM, Vincent Massol <[email protected]> wrote:

> Hi devs,
>
> Current release dates for 4.2 are:
>
> - 4.2M3: 3 sep 2012
> - 4.2RC1: 10 Sep 2012
> - 4.2Final: 17 Sep 2012
>
> Since we're already the 12th of Sep (i.e. late by **9** days on M3) his is
> obviously not going to happen… :(
>
> So I'd like to propose:
>
> - 4.2M3: 12th Sep 2012
> - 4.2RC1: 19th Sep 2012
> - 4.2Final: 24th Sep 2012
>
> Here's my +1
>
> Thanks
> -Vincent
>
> PS: I'd like not to postpone 4.2 final by more than 1 week because it
> means 4.3 will get shorter since we need to finish the 4.X cycle ASAP so
> that we can start the 5.x one as close as possible to the beginning of next
> year.
> _______________________________________________
> devs mailing list
> [email protected]
> http://lists.xwiki.org/mailman/listinfo/devs
>
_______________________________________________
devs mailing list
[email protected]
http://lists.xwiki.org/mailman/listinfo/devs

Reply via email to