One of the software projects I worked on... The lead eng reported it
will be done in two weeks, for about six weeks. Then WE looked at
what/how we were doing the job and took a different approach. it WAS
done in two weeks, but needed six weeks of data (micro code) entry. An
intern did the data entry.
I don't see (from what I read) the delay being a software/firmware
issue, but a hardware supply issue. AND, I would like to see the
supplier getting the product right (no replacements needed).
I did get "the" K4 email today.
*73, steve WB3LGC*
I see "this" as an opportunity for the "Easter Bunny" to bring a K4
upgrade from a K4 to a K4D...
On 1/16/20 3:19 PM, Gwen Patton wrote:
Murphy's Law of Cybernetic Entomology says: "There's always one more bug."
So "bug-free" is impossible.
Gwen, NG3P
______________________________________________________________
Elecraft mailing list
Home: http://mailman.qth.net/mailman/listinfo/elecraft
Help: http://mailman.qth.net/mmfaq.htm
Post: mailto:[email protected]
This list hosted by: http://www.qsl.net
Please help support this email list: http://www.qsl.net/donate.html
Message delivered to [email protected]