Nicolas Goaziou <[email protected]> writes:
> Hello,
>
> Malcolm Matalka <[email protected]> writes:
>
>> From what I can tell, those apply to CLOCKSUM but in this case I'm using
>> {:} for effort. Do they still apply there?
>
> They should, IIRC, as long as at least one duration is expressed using
> `org-effort-durations' units.
>
>> I can see that CLOCKSUM already uses days in the format but I'm not
>> seeing it on the output for Effort sums.
>
> Could you show an ECM if you think it doesn't work as expected?
Ohhhhhhhhhkay, now I get what's going on. It works if I have at least 1
effort estimate in days. What does not work is if the sum of effort
estimates sums up to over a day, it stays as hours. I don't know if
this behaviour is better or worse than my expected behaviour. For my
usecase I do have some estimates that are over a day but the legacy
behaviour would automatically convert.
Here is an example:
* Test1
:PROPERTIES:
:COLUMNS: %50ITEM(Task) %10Effort(Effort){:}
:END:
** Foo
:PROPERTIES:
:Effort: 8:00
:END:
** Bar
:PROPERTIES:
:Effort: 8:00
:END:
** Baz
:PROPERTIES:
:Effort: 8:00
:END:
This sums to 24:00, if I change 1 of these to 1d I get 3d (which is what
I want).
Thank you!
>