> On Apr 7, 2023, at 9:53 PM, David Masterson <dsmaster...@gmail.com> wrote:
> 
> Is there a way of creating a Task which is a once a week meeting that
> will take place in (say) June, July, and August and then stop repeating?
> 
> -- 
> David Masterson
> 

Not exactly the answer to the question, but I sometimes use the 
org-clone-subtree-with-time-shift function to copy a scheduled meeting. That 
will give me copies with the timestamps shifted by the amount requested 
(weekly, monthly, etc.). The advantage I found with this, is that I can then 
edit any of the copies to adjust for holidays.

Mark Barton