Carsten Dominik wrote:
On Nov 28, 2009, at 7:10 PM, Patrick Drechsler wrote:
Carsten Dominik wrote:
On Nov 28, 2009, at 4:51 PM, Patrick Drechsler wrote:
is it possible to skip weekends when rescheduling a task using the
"++1d" operator?
Example:
* TODO work task (not on weekends)
SCHEDULED: <2009-11-27 Fr ++1d>
When changing the state to the DONE state, it will be rescheduled to
the next day, no matter what day of the week that is. So changing
the example above to DONE on a Friday will reschedule the task for
Saturday. Is it possible to reschedule it for Monday?
no, this is not possible currently.
OK, thanks for the quick feedback.
Does this seem like a reasonable feature request?
> this sounds reasonable, but I don't currently have time to implement
> it. Would be interested in a patch, though.
"Learning E-Lisp" would be one of those tasks for the weekend. ;-)
Is there a separate bug-tracker/feature-request interface besides this ml?
Regards,
Patrick
_______________________________________________
Emacs-orgmode mailing list
Please use `Reply All' to send replies to the list.
Emacs-orgmode@gnu.org
http://lists.gnu.org/mailman/listinfo/emacs-orgmode