Mike, I have had instances on the manufacturing line were the unit would fail the Hipot or Ground Bond test. The same holds true. The power supply is an approved part and was tested by the power supply house. With this information alone I would recommend doing the tests on the end product.
Josh -----Original Message----- From: Mike Morrow [mailto:[email protected]] Sent: Thursday, August 31, 2000 10:40 AM To: EMC Society Subject: Why routine hipot is required. I've been asked why a routine hipot test is required on an end assembly computer when it uses a Listed power supply that has already been hipot tested. So far I don't like the way I've worded my response. Basically what I've said is that a power supply is approved as a component. The end safety of the device depends on the installation. Can anyone add some more beef to this statement. Thanks. Mike Morrow Senior Compliance Engineer Ucentric Systems 978-897-6482 [email protected] www.ucentric.com ------------------------------------------- This message is from the IEEE EMC Society Product Safety Technical Committee emc-pstc discussion list. To cancel your subscription, send mail to: [email protected] with the single line: unsubscribe emc-pstc For help, send mail to the list administrators: Jim Bacher: [email protected] Michael Garretson: [email protected] For policy questions, send mail to: Richard Nute: [email protected]