"I see your point, but as I understand it, only if the power pack is made
available with the apparatus to the end user, i.e. a system. This is up to
the manufacturer to define."

1.  Many 24 VAC products are shipped with a separate 230/24VAC transformer
unit that
plugs into the mains.  In this case, Surge testing is performed on the 230
Volt side of the transformer.

2.  Occasionally, products with a 24 VAC input are marketed without a
transformer.  Example:  small surveillance cameras.  Several of these
cameras are often installed in a factory or office, and the 24 VAC is
daisy-chained from a single 230/24 VAC transformer.  In this situation the
EMC Laboratory will often recommend that the camera manufacturer provide a
"typical" transformer that might be chosen by the end user.  Surge testing
is then performed on the 230 Volt side of this "representative" transformer.
And of course, the Test Report will clearly state the rationale for this
arrangement.

Jim Ericson
Acme Testing Company





-------------------------------------------
This message is from the IEEE EMC Society Product Safety
Technical Committee emc-pstc discussion list.

Visit our web site at:  http://www.ewh.ieee.org/soc/emcs/pstc/

To cancel your subscription, send mail to:
     [email protected]
with the single line:
     unsubscribe emc-pstc

For help, send mail to the list administrators:
     Michael Garretson:        [email protected]
     Dave Heald                [email protected]

For policy questions, send mail to:
     Richard Nute:           [email protected]
     Jim Bacher:             [email protected]

All emc-pstc postings are archived and searchable on the web at:
    No longer online until our new server is brought online and the old 
messages are imported into the new server.

Reply via email to