Hi All, Section 7.2.1.2 step 1 seems to be a method of determining the duty cycle of the EUT. This step calls for a diode detector for the measurement. My quick research shows this to be a fairly expensive accessory piece of equipment. I have a couple of questions. 1) What is the purpose of the diode detector? Normally I use a direct connection when measuring duty cycle? 2) I have tested RLAN products in Europe to this standard before, and the test house over there simply asked me what my duty cycle was. They never measured it. Is it permissible to show the duty cycle in the form of timing diagram instead. The FCC allows this.
Kind Regards, Sam Wismer Engineering Manager ACS, Inc. (Tel: (770) 831-8048 ÊFax: (770) 831-8598 :Web: www.acstestlab.com <http://www.acstestlab.com/> * <mailto:*[email protected]> [email protected]