Hi Grace,

The answer to your question has both a technical and a contractual 
component to it.

It becomes more difficult to fix any shielded room issues when tile is 
already installed. Fixes for shielding issues often affect a larger area 
when gasketing material or braces are to be replaced, sometimes panels 
if a penetration (or door) is the culprit. If the issue is pinpointed to 
a particular seam through experimentation, you would be relatively safe 
installing tile in the areas outside of the panels/mounting hardware 
associated with that seam. Other walls not affected by the shielding 
breach would be relatively safe as well. Shielding effectiveness testing 
at higher frequencies, if done correctly, is not negatively affected by 
absorbers mounted outside the immediate test area.

For most chamber builds not done by a single integrator, the shielded 
room contractor or installer is only responsible for delivery of an 
empty shielded room that meets shielding effectiveness specifications. 
Once someone else (absorber installer, customer) installs anything in 
that room, this clear responsibility becomes blurry since it can be 
argued that the continuing shield failure is completely or partially due 
to the added material or the installation process thereof. It is very 
difficult to argue against this without significant additional testing, 
which adds cost.

If the chamber installation is done by a chamber integrator, they are 
responsible for all aspects of performance so they would have to make 
the call on when it is appropriate to start the tile installation.

I would advise against installing tile before the shielded room meets 
the specification, unless you are absolutely sure doing so will not 
interfere with any contractual obligation on behalf of the shielded room 
manufacturer and/or installer.

One additional comment: Based upon my experience designing and building 
chambers as well as using them, I recommend clients to perform a 
shielding effectiveness verification after completion of the ferrite 
tile installation, before any foam absorbers go in. The reason for this 
is three-fold: Firstly, methods used for ferrite installation often 
require partially breaching the integrity of the shield. Secondly, the 
tile installation process can easily stress filter and other hardware 
installed. Thirdly, the weight of the ferrite tiles is considerable and 
will stress the room structure differently than when it is empty, 
possibly opening up seams. Note that this would mostly be an issue with 
lower quality (cheap) shielded room installations.

As product testing will be done in the absorber lined room it is always 
good to confirm the shielding quality of the final chamber, or at least 
close to it. The timing for the verification test (before any foam 
installation) is due to the need to be able to still fix issues and the 
ability to pinpoint issues. Once the foam is up fixing issues requires 
major tear-down work and it is not easy to get close to the wall for 
debug work.

Hope this helps.

Best regards,
-Robert

Grace Lin wrote:
> Dear Members,
>  
> Is it OK to start ferrite tile installation before the completion of 
> shielding test during the construction of a 3m EMC semi-anechoic 
> chamber?  More specifically, if a particular area, such as door seam, 
> does not meet the proposed specification, is it OK to start ferrite 
> tile installation on the area away from the door?  If yes, how far to 
> keep away from the door?
>  
> Thank you very much for your time and look forward to your help.
>  
> Best regards,
> Grace
> - ---------------------------------------------------------------- 
> This message is from the IEEE Product Safety Engineering Society 
> emc-pstc discussion list. Website: http://www.ieee-pses.org/
>
> To post a message to the list, send your e-mail to [email protected]
>
> Instructions: http://listserv.ieee.org/request/user-guide.html
>
> List rules: http://www.ieee-pses.org/listrules.html
>
> For help, send mail to the list administrators:
>
> Scott Douglas [email protected] Mike Cantwell [email protected]
>
> For policy questions, send mail to:
>
> Jim Bacher: [email protected] David Heald: [email protected]
>
> All emc-pstc postings are archived and searchable on the web at:
>
> http://www.ieeecommunities.org/emc-pstc
>

-

This message is from the IEEE Product Safety Engineering Society
emc-pstc discussion list.    Website:  http://www.ieee-pses.org/

To post a message to the list, send your e-mail to [email protected]

Instructions:  http://listserv.ieee.org/request/user-guide.html

List rules: http://www.ieee-pses.org/listrules.html

For help, send mail to the list administrators:

     Scott Douglas           [email protected]
     Mike Cantwell           [email protected]

For policy questions, send mail to:

     Jim Bacher:             [email protected]
     David Heald:            [email protected]

All emc-pstc postings are archived and searchable on the web at:

    http://www.ieeecommunities.org/emc-pstc

Reply via email to