One LISN per power cord is acceptable.  One power cord per LISN is required
for the power cord being measured.  That way you know that the emissions being
measured are from that cord, and not another one.  

 

This was simpler with the old design – two cords comes out of the cabinet,
each to its own LISN.  Now John has to contend with a bunch of cords.  This is
addressed in CISPR 22, article 9.5.1, which states:

 

“The mains cable of the unit being measured shall be connected to one
artificial mains network (AMN).  Where the EUT is a system, which is a
collection of ITE with one or more host units, and each item has its own power
cable, the point of connection for the AMN is determined by the following
rules:

 

a)  Each power cable that is terminated in a power supply plug of a standard
design (IEC 60083 for example) shall be tested separately.”

 

There is no question that the power cords are tested one at a time.  A later
paragraph in 9.5.1 calls for one or more additional AMNs for the additional
power cables.

 

Article 7.2.1 of ANSI C63.4:2003 has different text that conveys the same
message.

 

So, if your thought is to be accepted, both ANSI C63.4 and CISPR 22 (and
probably other standards, as well) will have to be changed.  Given the success
in reducing or largely eliminating interference from ITE that the current
standards have demonstrated over the past 20+ years, I doubt that will gain
much traction.  At least, I certainly hope not.  :-)

 

Ghery S. Pettit, NCE

Convener, CISPR SC I WG3

Member, C63 SC 1

 

 

________________________________

From: [email protected] [mailto:[email protected]] On Behalf Of Ken Javor
Sent: Tuesday, June 03, 2008 2:09 PM
To: Untitled
Subject: Re: Placement of LISNs for Conducted Emissions Testing to CISPR22/FCC
part 15

 

First a direct response to the question posed, then a challenge to the premise
upon which it is based. The second comment, if legitimate, is more important
than the first.

You could use one dual LISN, or one LISN per current-carrying power conductor,
if you had eighteen different make-before-break switches that would allow each
power cord to draw current either from the LISN power output port, or the LISN
input power side.  If you want to go with eighteen LISNs, I think it is
technically acceptable to stack them, but you want the ground strap to
maintain a lower than 5:1 length-to-width ratio, so that likely means stacking
no more than three high.

But here’s an interesting and likely unwelcome thought, which I invite other
forum members to comment upon. The point of meeting a conducted emissions
requirement is to protect radios operating below 30 MHz that might be powered
>from the same branch circuit, or in the case of class A which likely applies
here, operated within some distance of the equipment, but plugged into a
different branch.  If the equipment in your two racks operates simultaneously,
it isn’t obvious to me that you are even allowed different LISNs –
presumably all your rack equipment plugs into the same branch circuit, which
should be represented by a single pair of LISNs.  Immediate problem solved,
but potentially more noise to filter, especially if power supplies operating
off each cord operate at same switching frequencies.
 
Ken Javor

Phone: (256) 650-5261



________________________________

From: "Flavin, John" <[email protected]>
List-Post: [email protected]
List-Post: [email protected]
List-Post: [email protected]
Date: Tue, 3 Jun 2008 16:40:10 -0400
To: <[email protected]>
Conversation: Placement of LISNs for Conducted Emissions Testing to
CISPR22/FCC part 15
Subject: Placement of LISNs for Conducted Emissions Testing to CISPR22/FCC
part 15



Our company sells ITE systems that are housed in commerial 19" racks. The
system is designed to be fault tolerant and redundant, so each rack has two AC
mains cords. 

We do our own EMI certification testing (we're an accreditted lab), and our
typical EUT consists of two of these rack, so there are 4 AC Mains cords to
test, which we connect to 4 LISNs.

A modified version of this system is now in the works, where the dual AC mains
cords are replaced by multiple cords (with lower current per cord). The design
now would have 10 AC mains cords out of one rack, and 8 from the other. This
means the two rack EUT would have 18 AC Mains cords to test. 

In a perfect world, where cost were no object, we would have 18 LISNs, since
this is the most efficient for testing -- set it up once, and test everything.

Our question is how to place a relatively large number of LISNs and satisfy
the standards' requirement of the 80cm spacing of the EUT and LISN.
Specifically:

1) Are we allowed to place LISNs around all sides of the EUT, maintaining the
80cm spacing (i.e. have LISNs at the front face of the EUT, and run the mains
cord from the back to the LISN)?

2) Are we allowed to stack LISNs on top of each other, as long as the LISN is
bonded to the ground plane? 

Since we have to test each cord in turn, we could reduce the number of LISNs
by combining a number of the cords not currently being tested through a second
(or third) LISN. The downside of this is having to re-plug the cords after
each cord is tested, which requires shutting the system down and restarting,
which is a non-trivial task (and takes longer than it does to test one cord).


John D. Flavin 
Teradata TCP Engineering 
17095 Via del Campo 
San Diego, CA 92127 
[email protected] 
V: (858) 485-3874 
F: (213) 337-5432 
- ---------------------------------------------------------------- This
message is from the IEEE Product Safety Engineering Society emc-pstc
discussion list.    Website:  http://www.ieee-pses.org/ 

To post a message to the list, send your e-mail to [email protected] 

Instructions:  http://listserv.ieee.org/request/user-guide.html 

List rules: http://www.ieee-pses.org/listrules.html 

For help, send mail to the list administrators: 

 Scott Douglas           [email protected] Mike Cantwell          
[email protected] 

For policy questions, send mail to: 

 Jim Bacher:             [email protected] David Heald:           
[email protected] 

All emc-pstc postings are archived and searchable on the web at: 

 http://www.ieeecommunities.org/emc-pstc

- ---------------------------------------------------------------- This
message is from the IEEE Product Safety Engineering Society emc-pstc
discussion list. Website: http://www.ieee-pses.org/ 

To post a message to the list, send your e-mail to [email protected] 

Instructions: http://listserv.ieee.org/request/user-guide.html 

List rules: http://www.ieee-pses.org/listrules.html 

For help, send mail to the list administrators: 

Scott Douglas [email protected] Mike Cantwell [email protected] 

For policy questions, send mail to: 

Jim Bacher: [email protected] David Heald: [email protected] 

All emc-pstc postings are archived and searchable on the web at: 

http://www.ieeecommunities.org/emc-pstc -
---------------------------------------------------------------- This message
is from the IEEE Product Safety Engineering Society emc-pstc discussion list.
Website: http://www.ieee-pses.org/ 

To post a message to the list, send your e-mail to [email protected] 

Instructions: http://listserv.ieee.org/request/user-guide.html 

List rules: http://www.ieee-pses.org/listrules.html 

For help, send mail to the list administrators: 

Scott Douglas [email protected] Mike Cantwell [email protected] 

For policy questions, send mail to: 

Jim Bacher: [email protected] David Heald: [email protected] 

All emc-pstc postings are archived and searchable on the web at: 

http://www.ieeecommunities.org/emc-pstc 

Reply via email to