hey

On Fri, Jul 5, 2019 at 11:24 AM Carsten Haitzler <[email protected]> wrote:
>
> On Fri, 28 Jun 2019 12:24:14 +0200 Stefan Schmidt <[email protected]>
> said:
>
> > Hello.
> >
> > Its almost 3 months since we released 1.22 so its time to talk about the
> > release schedule for 1.23 again
> >
> > I promised/discussed before 1.22 we wanted to have longer release cycle
> > as three months was just to hard. I would aim for a bit over 4 months
> > this time and we can adjust again afterwards.
>
> I think this seems fine.
>
> > Mike did much of the work for the last release and he promised to spent
> > some time on it again. Much appreciated. Other are more than welcome to
> > get all parts solid for the release as well. :-)
> >
> > Here is my release schedule proposal to get us started. Comments?
> >
> > === Schedule ===
> > 2019-04-05 1.22 release / merge window for 1.23 opens
> > 2019-08-26 Notice about soon ending merge window
> > 2019-09-02 Merge window is over. Freeze in place.
> > * Only bug fixes from this point
> > * Alpha release tarball
> > 2019-09-09 Beta1 release tarball
> > * Only critical fixes from this point
> > 2019-09-16 Beta2 release tarball
> > 2019-09-23 EFL 1.22 is out
>
> I was planning to get an E 0.23 out and after that look into the server
> situation as this would require bringing services down for a while to do a
> move. Well it seems things are down anyway, so I think this is going to put a
> bit of a dent in a timetable like the above. Just be prepared for some upsets
> in infra.

because of the server being down during one week, what about
postponing all the schedule by 1 week ?

Vincent


_______________________________________________
enlightenment-devel mailing list
[email protected]
https://lists.sourceforge.net/lists/listinfo/enlightenment-devel

Reply via email to