On 03/03/16 11:02, Stefan Schmidt wrote:
> Hello.
>
> On 03/03/16 11:46, Tom Hacohen wrote:
>> On 03/03/16 10:41, Stefan Schmidt wrote:
>>> Hello.
>>>
>>> Some people might be wondering why there was no schedule for 1.18 yet
>>> while we are already in the development phase of it after 1.17 was
>>> released. The simple reason is that 1.18 will be different from the
>>> normal 3 months rhythm we had the last 9 (!) release cycles. It should
>>> be an exception though and we should go back to the normal rhythm with 1.19.
>>>
>>> 1.18 will be on a longer schedule as we have two major things we need to
>>> coordinate together and that would just not work in our three months
>>> schedule. We are merging Elementary into EFL and getting the EFL
>>> Interface (aka EFL 2.0 API) finalised.
>>>
>>> If you have comments please let me know. I will give it a week to gather
>>> comments before making it final.
>>>
>>> === Schedule ===
>>> 2016-02-02 Merge window for 1.18 opens
>>> (2016-05-14 Enlightenment Developer Days in Paris. This should be the
>>> point where the major work is done and we discuss left overs and how to
>>> fix them for 1.18)
>>> 2016-05-17 Technical preview tarballs for packagers
>>> 2016-05-30 Notice about soon ending merge window
>>> 2016-06-06 Merge window is over.
>>> * Only bug fixes from this point
>>> * Alpha release tarball
>>> * One month stabilization phase starts
>>> 2016-06-13 Beta1 release tarball
>>> * Only critical fixes from this point
>>> 2016-06-20 Beta2 release tarball
>>> 2016-06-27 Beta3 release tarball
>>> 2016-07-04 EFL 1.18 is out (First Monday in July)
>>>
>>> https://phab.enlightenment.org/w/efl_and_elementary_1_18/
>> Looks good, and I guess that since there is less than a month until the
>> 1.20 release date after 1.19, we will probably extend the 1.20 by that
>> time too, which is fine.
>
> Good point. I haven't mentioned that. The longer schedule means we also
> need to adapt the following schedules.
>
> In mid term I would like to come back to the 3 months rhythm with
> February, May, August and November as it did fit well with public
> holidays, normal vacation schedule etc. 1.19 at least will not be
> aligned to that. I have not made up my mind for the rest. Waiting how
> 1.18 turns out and if we are still on schedule at that point is properly
> best before we decide.

Sorry, I got the version wrong, I meant 1.19 wouldn't exactly be the 
same date, it would be a bit longer, but same release date. So it'd be a 
bit over 3 months, but at least back to the normal schedule.

--
Tom.


------------------------------------------------------------------------------
Site24x7 APM Insight: Get Deep Visibility into Application Performance
APM + Mobile APM + RUM: Monitor 3 App instances at just $35/Month
Monitor end-to-end web transactions and take corrective actions now
Troubleshoot faster and improve end-user experience. Signup Now!
http://pubads.g.doubleclick.net/gampad/clk?id=272487151&iu=/4140
_______________________________________________