Mark

 

Well raised, I think this is an area that needs clarification.

 

Maybe I'm having a bad sight day, but I'm in the same boat as you......

First of all, I don't think there is any explicit mention of
prioritizing requirements as an entity, but prioritizing items in the
WIL (including requirements) is covered partially.

 

Certainly the Project Manager, as primary performer of Task: 'Plan
Iteration' uses the Stakeholder prioritization as a necessary input into
that task, but the steps in the task itself could be interpreted in a
couple of different ways.

 

Note my highlighting in Red below.

 

 
<file:///F:\Telelogic\Product%20Management\EPF\OpenUP_Basic_published-0.
9-W-20070216\Publish\openup_basic\tasks\plan_iteration,_0keUEMlgEdmt3adZ
L5Dmdw.html> Define the iteration objectives  

At the beginning of an iteration, the Role: Project Manager
<file:///F:\Telelogic\Product%20Management\EPF\OpenUP_Basic_published-0.
9-W-20070216\Publish\openup_basic\roles\project_manager,_0a0o0MlgEdmt3ad
ZL5Dmdw.html>  works with the team to define 1-5 objectives. These
objectives should be a refinement of the iteration objectives found in
the Artifact: Project Plan
<file:///F:\Telelogic\Product%20Management\EPF\OpenUP_Basic_published-0.
9-W-20070216\Publish\openup_basic\workproducts\project_plan,_0a6vcMlgEdm
t3adZL5Dmdw.html> , and should provide high-level direction to what
should be targeted for the iteration. The objectives should be driven
based on Role: Stakeholder
<file:///F:\Telelogic\Product%20Management\EPF\OpenUP_Basic_published-0.
9-W-20070216\Publish\openup_basic\roles\stakeholder,_dTa6gMAYEdqX-s4mWhk
yqQ.html>  priorities, and will be revised as the iteration plan is
finalized. The objectives are usually defined as high-level capabilities
or scenarios that need to be implemented and tested during the
iteration.

 
<file:///F:\Telelogic\Product%20Management\EPF\OpenUP_Basic_published-0.
9-W-20070216\Publish\openup_basic\tasks\plan_iteration,_0keUEMlgEdmt3adZ
L5Dmdw.html> Produce detailed plan  

The Role: Project Manager
<file:///F:\Telelogic\Product%20Management\EPF\OpenUP_Basic_published-0.
9-W-20070216\Publish\openup_basic\roles\project_manager,_0a0o0MlgEdmt3ad
ZL5Dmdw.html>  works with the rest of the team, and especially the
project stakeholders, to identify the high-priority work items from the 
Artifact: Work Items List
<file:///F:\Telelogic\Product%20Management\EPF\OpenUP_Basic_published-0.
9-W-20070216\Publish\openup_basic\workproducts\work_items_list,_rGNWsCbS
Edqh1LYUOGRh2A.html>  to be addressed within the iteration. The
high-level objectives provide guidance on what work items should be
considered. The team should break down work items so they fit within the
iteration as necessary. Actual effort to complete each Work Item should
be estimated. When a team has decided to take on a Work Item, it will
assign the work to one or several team members. Ideally, this is done by
team members signing up to do the work, since this makes people
motivated and committed to doing the job, but based on culture, you may
instead have the project manager assign the work.

 

With the first step, it is ambiguous (to me at least) as to whether the
prioritization has already occurred elsewhere or not.

 

With the second step, it is implied that that the prioritization is
happening here in this step (or why would we need to work with
'especially the project stakeholders'?)

 

The following exists within Task: 'Define Vision':

 

 
<file:///F:\Telelogic\Product%20Management\EPF\OpenUP_Basic_published-0.
9-W-20070216\Publish\openup_basic\tasks\define_vision,_0fOAoMlgEdmt3adZL
5Dmdw.html> Define features of the system  

Work with stakeholders to capture a list of features
<file:///F:\Telelogic\Product%20Management\EPF\OpenUP_Basic_published-0.
9-W-20070216\Publish\openup_basic\guidances\termdefinitions\feature,_PgY
REAeYEduWycDgioo5rg.html>  that stakeholders want in the system, briefly
describing them and giving attributes to help define their general
status and priority in the project.

 

The Task: 'Find and Outline Requirements' contains:

 

 
<file:///F:\Telelogic\Product%20Management\EPF\OpenUP_Basic_published-0.
9-W-20070216\Publish\openup_basic\tasks\find_and_outline_requirements,_P
9cMUPV_EdmdHa9MmVPgqQ.html> Update the Work Items List  

Capture references to the requirements in the Artifact: Work Items List
<file:///F:\Telelogic\Product%20Management\EPF\OpenUP_Basic_published-0.
9-W-20070216\Publish\openup_basic\workproducts\work_items_list,_rGNWsCbS
Edqh1LYUOGRh2A.html> , so that you can prioritize the work.

 

The WIL artifact of course has the following Purpose field:

 
<file:///F:\Telelogic\Product%20Management\EPF\OpenUP_Basic_published-0.
9-W-20070216\Publish\openup_basic\workproducts\work_items_list,_rGNWsCbS
Edqh1LYUOGRh2A.html> Purpose  

To collect all requests for work that will potentially be taken on
within the project, so work can be prioritized, effort estimated and
progress tracked.

 

And the following exists in the Main Description of the WIL artifact:

 

*         It provides one list of all the work to be prioritized,
estimated, and assigned within the project. The risk list is prioritized
separately.

 

In summary, I think prioritization of items in the WIL should be an
explicit step somewhere (perhaps in 'Plan Iteration' ?), and other
references to prioritization should be cleaned up.

 

Ben

 

 

> -----Original Message-----

> From: [EMAIL PROTECTED] [mailto:[EMAIL PROTECTED]

> On Behalf Of [EMAIL PROTECTED]

> Sent: 12 March 2007 14:26

> To: [email protected]

> Subject: [epf-dev] Prioritizing requirements

> 

> Quick question;

> 

> Can someone tell me briefly where in OpenUP/Basic we describe

> requirements

> prioritization? Who is the primary performer and what Task is it

> described

> in? I've flipped though the obvious places in the content but I may
have

> missed it.

> 

> Traditionally in the Unified Process it is something that the
Architect

> has

> been responsible for within Requirements workflows, hence my interest.

> 

> thanks

> 

> Mark

> 

> Mark Dickson

> Executive Consultant

> EAS Practice

> m 0780 1917480

> w www.xansa.com

> e [EMAIL PROTECTED]

> 

> 

> Whilst this email has been checked for all known viruses, recipients

> should undertake their own virus checking as Xansa will not accept any

> liability whatsoever.

> 

> This email and any files transmitted with it are confidential and

> protected by client privilege.  It is solely for the use of the
intended

> recipient.

> Please delete it and notify the sender if you have received it in

> error. Unauthorised use is prohibited.

> 

> Any opinions expressed in this email are those of the individual and
not

> necessarily the organisation.

>      Xansa, Registered Office: 420 Thames Valley Park Drive,

>      Thames Valley Park, Reading, RG6 1PU, UK.

>      Registered in England No.1000954.

>      t  +44 (0)8702 416181

>      w  www.xansa.com

> _______________________________________________

> epf-dev mailing list

> [email protected]

> https://dev.eclipse.org/mailman/listinfo/epf-dev

 

 

------------------------------------------------------------------------
--------
Telelogic Lifecycle Solutions:
Helping You Define, Design & Deliver Advanced Systems & Software
Learn More at www.telelogic.com <http://www.telelogic.com/> 

 

Ben Williams 
Product Manager, Lifecycle Solutions
Telelogic UK Ltd, Northbrook House, Oxford Science Park, Oxford, OX4
4GA, United Kingdom
Phone: +44 (7710) 637 067
Fax: +44 (1865) 784 286
Mobile phone: +44 (7710) 637 067

[EMAIL PROTECTED]
http://www.telelogic.com <http://www.telelogic.com/> 

Telelogic - Requirements-Driven Innovation!
------------------------------------------------------------- 

 

 

The information contained in this e-mail, including any attachment or
enclosure, is intended only for the person or entity to which it is
addressed and may contain confidential material. Any unauthorized use,
review, retransmissions, dissemination, copying or other use of this
information by persons or entities other than the intended recipient is
prohibited. 

  

Attachment: image001.gif
Description: image001.gif

_______________________________________________
epf-dev mailing list
[email protected]
https://dev.eclipse.org/mailman/listinfo/epf-dev

Reply via email to