Here's a summary of the iteration assessment we had today. Please let me 
know if I missed any information.
Thanks,

Ricardo.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Iteration C2 Assessment and Iteration T1 Planning

Assessment target
C2 Iteration
Assessment date
7/30/08
Participants
Ricardo Balduino, Felix de Onandia, Bruce MacIsaac, Ken Clyne, and Mark 
Dickson.

[Nate Oster, Kim Werner, and Chris Sibbald are on vacation (back on mid 
August)
Ana Pereira had a schedule conflict and wasn't able to join.]
Project status
Yellow ? we have 40 bugs in new/assigned state


Assessment against objectives

Architecture practice ? 4 bugs are unresolved. Two are trivial. Three will 
be addressed by Mark and 1 by another contributor.
PM practices ? 9 bugs left. Ricardo and Ana will address those bugs, but 
extra help is always welcome. 
Other practice owners weren't available to report status.
Other concerns and deviations
We need to motivate people to finish an amount of bugs per week on the 
next 3 weeks otherwise we won?t finish all planned work on this release.
Felix will send note asking each content author what is realistic about 
finishing their bugs by the release date. If they can?t do it, we will 
have to find a contingency plan (other volunteers? drop features?). Each 
person gives estimate on how much time they need to finish. Each person 
shows plan to complete bugs. If not feasible, we can try allocating bugs 
to other people. 
We should freeze content one week before release. Freeze on 15th and do 
test until 17th. From 18th through 20th, we will do fixing and polishing 
of the content.
In two weeks all bugzillas should be at least in resolved state.
Nate and Kim are out until 15th, who can take their bugs over? ? ask Jim 
and Dan about contingency plan. If there isn't one, ask epf-dev for help.
Only 2 practice owners (thanks Mark and Ana) sent list of contributors on 
their practices. We need this from everyone so we can pass the Eclipse 
Release Review. This material needs to be in place one month before the 
release, so we are clearly running short on time.