Eclipse Oxygen M3 Stabilization starts next week with a goal to deliver on
Oct 28, 2016. 

The build schedule has been updated and can be downloaded from here

Please note 

*         Monday we have the last day of development (and even then, no
"big changes"). After Monday, no feature work or unrelated fixes are
allowed -- only regression fixes.

*         Tuesday all day test pass . No one should develop or fix
anything, but literally spend the entire day testing.

*         Wednesday is the fix-day with a focus on fixing regressions
found during the test-day(tuesday). No unrelated fixes

*         The last Wednesday build is the release candidate every team
signs-off on Thursday. Signing-off may involve some re-testing, or at
least confirming no changes have been made to your components code since
the last time the component was tested well.

No new code changes can be made until the milestone is officially
declared. That is, it is not enough that your component has signed off.


Thanks and Regards,



Sravan Kumar Lakkimsetti

IBM India Pvt Ltd,

Embassy Golf Links Business Park, D Block,

Off Indiranagar-Kormangla Inner Ring Road,

Bangalore - 560071, India

Phone: 91-80-41776858