Hi Folks,
It's the milestone week - 4.12 M3.

Monday: Last day of development (and even then, no "big changes"). After 
Monday 18:00 ET, no feature work or unrelated fixes are allowed -- only 
regression fixes.
Tuesday: All-day test pass. Nobody should develop or fix anything. 
Literally spend the entire day testing.
Wednesday: Fix day with a focus on fixing regressions found during the 
test day (Tuesday). No unrelated fixes. Review and thoroughly test all 
commits.
The last Wednesday build is the release candidate every team signs off on 
Thursday.
The "New and Noteworthy" entries are due on Wednesday evening:
Git repo: ssh://git.eclipse.org/gitroot/www.eclipse.org/eclipse/news.git
Gerrit: ssh://git.eclipse.org:29418/www.eclipse.org/eclipse/news.git
Live website: https://www.eclipse.org/eclipse/news/4.12/
Thursday: Sign-off after re-testing, or at least confirming no changes 
have been made to your component's code since the last time the component 
was tested well.
Friday: Build is officially declared and made available.
The master branch stays closed until the milestone is officially released. 
(That is, it is not enough that your component has signed off.)


NOTE: This is the last "normal" milestone. After that we will enter the 
endgame. Endgame plan will follow.

Dani

_______________________________________________
equinox-dev mailing list
[email protected]
To change your delivery options, retrieve your password, or unsubscribe from 
this list, visit
https://www.eclipse.org/mailman/listinfo/equinox-dev

Reply via email to