Hi,
It's the milestone week - 4.13 M1.
         Monday: Last day of development (and even then, no "big changes").
         After Monday 18:00 ET, no feature work or unrelated fixes are
         allowed -- only regression fixes.
         Tuesday: All-day test pass. Nobody should develop or fix anything.
         Literally spend the entire day testing.
         Wednesday: Fix day with a focus on fixing regressions found during
         the test day (Tuesday). No unrelated fixes. Review and thoroughly
         test all commits.
            The last Wednesday build is the release candidate every team
            signs off on Thursday.
            The "New and Noteworthy" entries are due on Wednesday evening:
            Git repo:
            ssh://git.eclipse.org/gitroot/www.eclipse.org/eclipse/news.git
            Gerrit:
            ssh://git.eclipse.org:29418/www.eclipse.org/eclipse/news.git
            Live website: https://www.eclipse.org/eclipse/news/4.13/
         Thursday: Sign-off after re-testing, or at least confirming no
         changes have been made to your component's code since the last
         time the component was tested well.
         Friday: Build is officially declared and made available.
         The master branch stays closed until the milestone is officially
         released. (That is, it is not enough that your component has
         signed off.)

Thanks & Regards,
Sarika
_______________________________________________
equinox-dev mailing list
equinox-dev@eclipse.org
To change your delivery options, retrieve your password, or unsubscribe from 
this list, visit
https://www.eclipse.org/mailman/listinfo/equinox-dev

Reply via email to