Howdy all--
Well, I started out with the best of intentions ;-). I worked out my
schedule so that I could cram all my work into the last week of the
sprint. Then I had a number of unexpected priorities and delays,
leading to the last week being filled.
I have about a day's worth of work to do to finish up a design for a
client, then I hope to spend the last four days of next week
(finally) working on ESME. My plan is to sign the iCLA and work on
a preliminary UI spec for the web client. Hope I can get enough done
next week, because the week after I start a contract with a new
client.
Regards,
Bill
At 10:23 AM +0100 2/6/09, Hirsch, Richard wrote:
Our first sprint ends today and I'd like to know the status of the tasks:
Here are the items that we planned and their status to the best of my
knowledge.
User Interface:
General User Interface (UI) roadmap with order of goals and what
needs to be accomplished
Adequate description of User Interface architecture
Creation of first sprint specification
Partial implementation (Web Interface)
--
======================================================================
Bill Fernandez * User Interface Architect * Bill Fernandez Design
(505) 346-3080 * [email protected] * http://billfernandez.com
======================================================================