Howdy all--

Well, I started out with the best of intentions ;-). I worked out my schedule so that I could cram all my work into the last week of the sprint. Then I had a number of unexpected priorities and delays, leading to the last week being filled.

I have about a day's worth of work to do to finish up a design for a client, then I hope to spend the last four days of next week (finally) working on ESME. My plan is to sign the iCLA and work on a preliminary UI spec for the web client. Hope I can get enough done next week, because the week after I start a contract with a new client.

Regards,
Bill


At 10:23 AM +0100 2/6/09, Hirsch, Richard wrote:

Our first sprint ends today and I'd like to know the status of the tasks:

Here are the items that we planned and their status to the best of my knowledge.

User Interface:

General User Interface (UI) roadmap with order of goals and what needs to be accomplished
Adequate description of User Interface architecture
Creation of first sprint specification
Partial implementation  (Web Interface)


--

======================================================================