Hal Rosenstock wrote:
On Mon, 2008-06-16 at 16:59 +0300, Tziporet Koren wrote:
My proposal is to do the feature freeze closer to 2.6 27 - at middle
of July

What does the schedule/projected end date then look like ? Does this
impact any deliverables to SC or Plugfest/interop events ?

-- Hal


I think no
The schedule should be:

Ø

   * Alpha: Jul 15, 08 - feature freeze
   * Beta: Jul 30, 08 - kernel 2.6.27-rcX (assuming it will be available)
   * RC1: Aug 13, 08
   * RC2: Aug 27, 08
   * RC3-RC5/6 – every 5-10 days
         o Latest RC to be used in OFA interop event
   * GA: Oct 06 08

Tziporet