Hello,

I have some requirement so when i am working on RHEL7.2 OS release, i sync 
repos daily night and run some CI jobs and publish and promote CV version 
as per success of jobs.

now when RHEL7.3 OS is ready to release, i want to freeze sync for RHEL7.2 
CV and below is what i think i should be doing

1) i will create filter with "Include all rmps" and "include all errata up 
to today's date" ... 

2) publish CV, and promote it to all life cycle envs 

3) now i will start updating 7.3 CV till 7.4 releases .. 

4) if any bug fix or erratas comes in, i will "include" that in 7.2 CV 
(filters) and publish.



Now question i have is, when i do step 1 above, is it good step to freeze 
CV? is that CV version will be same as earlier version (before filters) ? 


Do i need to include "package groups" or it automatically include those ?


whenever new erratas come in, i will change "Errata" date or include 
another filter to include errata date to today, and publish CV, when i 
publish CV will it change any RPM version as well ? ( apart from errata? , 
for example kernel rpm version )


Does anyone have some better way of doing it?


Thanks,
DJ






-- 
You received this message because you are subscribed to the Google Groups 
"Foreman users" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send email to [email protected].
Visit this group at https://groups.google.com/group/foreman-users.
For more options, visit https://groups.google.com/d/optout.

Reply via email to