I've gone through the process page and spruced it up. The main change is
that I've split things into three JIRA tickets, but removed all the
suggestion of many sub-tickets.

The three are:

1) Retiring the project.
2) Deleting the resources.
3) Deleting the resources, 6 months later.

#2 and #3 should be an issue opened with INFRA.

My thinking is that the items in #1 are critical to informing users that
the project is defunct, and making sure the project doesn't continue as a
zombie, while #2 and #3 are largely about saving ASF resources and cleaning
up. I imagine there'll be debate about what should be in #1 and #2.
Currently I've arbitrarily gone with #1 being those items any member can do
(filtered by what I knew how to do).

I've also checked Muse off as complete, and moved Esme, Stdcxx and XMLBeans
along.

Hen