> >>Projects Successes Failures Prereqs No Works Packages
> >>563 01 (0.18%) 00 (0.00%) 00 (0.00%) 512 (90.94%) 50 (8.88%)
> Currently the success is showing as:
>
> Overall project success : 9.06%
The 50 at the end are actually packaged *projects* (not simply modules in a
Gump sense). See:
http://brutus.apache.org/gump/public/packages.html#Packaged+Projects
> This suggests that No Work entries may be factored into the calculation
> of success.
Depends upon if you consider a packaged project a "no work" or not. I chose
to include it as work, because even thought it never shows as a success
(Gump doesn't build it) it can count as a failure (if incorrectly
installed/missing). As such 'overal success' is projects plus sucessfully
installed packged projects.
> From a total of 563 projects, 512 were counted as no-work -
> leaving a total of 51 projects.
Yup, the one done (to that point) plus those 50 packaged projects.
> 51/563 = 0.091
Or 0.0906 (to give 9.06%).
> But looking at the other numbers, 50 of these remaining projects are
> modules. So in fact the the success ratio calculation is being skewed by
> the inclusion of modules.
Hey, we are cutting the Gumpmeisters some slack for correctly installing the
package (and keeping them maintained). I'm not trying to skew, so I'll
adjust if folks feel strongly, but this seems the right calculation to me.
Thanks for looking closely at the numbers. :-)
regards,
Adam
---------------------------------------------------------------------
To unsubscribe, e-mail: [EMAIL PROTECTED]