Sorry for the delay. I will be submitting this report end of today. Please update or let me know if you think something is missing.

-Mark

----- Original Message ----- From: <[EMAIL PROTECTED]>
To: <[EMAIL PROTECTED]>
Sent: Tuesday, August 30, 2005 8:07 AM
Subject: cvs commit: logging-site/docs/BoardReports board-report-2005-08.txt


mwomack     2005/08/30 08:07:07

 Modified:    docs/BoardReports board-report-2005-08.txt
 Log:
 Updated various reports.

 Revision  Changes    Path
1.3 +23 -4 logging-site/docs/BoardReports/board-report-2005-08.txt

 Index: board-report-2005-08.txt
 ===================================================================
RCS file: /home/cvs/logging-site/docs/BoardReports/board-report-2005-08.txt,v
 retrieving revision 1.2
 retrieving revision 1.3
 diff -u -r1.2 -r1.3
 --- board-report-2005-08.txt 23 Aug 2005 10:11:45 -0000 1.2
 +++ board-report-2005-08.txt 30 Aug 2005 15:07:07 -0000 1.3
 @@ -7,19 +7,38 @@
  PMC Report
  ----------

 -** TBD **
 +* PMC continues to track LS projects under incubation: log4net, log4php.
 +
+* Planning project-wide switch to SVN sometime during the month of September.
 +
 +* Submitted a LS BoF session for the upcoming ApacheCon US 2005.


  log4cxx Report
  --------------

 -** TBD **
 +* A release is still long overdue, however most major issues have been
 +resolved and remaining tasks primarily involve restoring functionality
 +that had been disabled during recent pervasive changes.  Jira issue
 +LOGCXX-62 is tracking the progress toward an 0.9.8 release.
 +
 +* Still tracking contributors for possible committer status.  May submit
 +candidate to LS PMC for vote during September.


  log4j Report
  ------------

 -** TBD **
 +* Released v1.2.11 as a minor release.
 +
+* Currently in the process of releasing v1.2.12 which contains a number of +bug fixes and the long awaited TRACE level. Also fixes build issues where +v1.2.11 was not very compatible with JDK 1.2 or earlier due to it being built
 +with JDK 1.4 instead of JDK 1.3.
 +
+* Plan to start on v1.3 tasks and issues immediately after the SVN migration. +v1.3 will be the next major release. Would like to release it before the end
 +of the year, but there are many tasks to review and work on.


  log4net Report
 @@ -39,5 +58,5 @@
  log4php Report
  --------------

 -** TBD **
 +* No report submitted, will follow up with subproject.







Reply via email to