Neels Hofmeyr has posted comments on this change. (
https://gerrit.osmocom.org/11733 )
Change subject: BSC_Tests: expect a HANDOVER PERFORMED message on internal
handover
......................................................................
Patch Set 3:
let's see...
OK you're right. The spec says that during Assignment we send no HANDOVER
PERFORMED message (duh!), but even during a handover within the same cell (not
even changing the BTS), we actually *do* send a HANDOVER PERFORMED message:
48.008 3.1.1.1 (Assignment / success)
"If an intra-BSS cell change has
occurred during the assignment, the new cell identity is included in the
ASSIGNMENT COMPLETE message and a
HANDOVER PERFORMED message is not required."
3.1.6 Internal Intra-Cell Handover Procedure
and same at
3.1.7 Internal Inter-Cell Handover Procedure
Internal {intra,inter}-cell handover [...] is decided and executed autonomously
by the
BSS, so that no message is generated at the BSS-MSC interface, until the
completion of the handover execution, when
the BSS sends a HANDOVER PERFORMED message over the SCCP and terrestrial
resources that are presently
assigned to that call. Changes in type of resources (for instance channel rate
change, speech version change, ciphering
algorithm change) are indicated in the HANDOVER PERFORMED message.
--
To view, visit https://gerrit.osmocom.org/11733
To unsubscribe, or for help writing mail filters, visit
https://gerrit.osmocom.org/settings
Gerrit-Project: osmo-ttcn3-hacks
Gerrit-Branch: master
Gerrit-MessageType: comment
Gerrit-Change-Id: I10f4e578c96a90317939ba49b61b14a3c7e488a7
Gerrit-Change-Number: 11733
Gerrit-PatchSet: 3
Gerrit-Owner: dexter <[email protected]>
Gerrit-Reviewer: Harald Welte <[email protected]>
Gerrit-Reviewer: Jenkins Builder (1000002)
Gerrit-Reviewer: Neels Hofmeyr <[email protected]>
Gerrit-Reviewer: dexter <[email protected]>
Gerrit-Comment-Date: Mon, 19 Nov 2018 16:21:56 +0000
Gerrit-HasComments: No
Gerrit-HasLabels: No