On Mon, May 30, 2016 at 7:07 AM, Vijay Bellur <vbel...@redhat.com> wrote:
> Since we do not have any objections to this proposal, let us do the
> following for 3.7.12:
>
> 1. Treat June 1st as the cut-off for patch acceptance in release-3.7.
> 2. I will tag 3.7.12rc1 on June 2nd.
> 3. All maintainers to ack content and stability of components by June 9th.
> 4. Release 3.7.12 around June 9th after we have all acks in place.

Would 3 days be sufficient to get the content for the website and a
bit of PR written up?

-- 
sankarshan mukhopadhyay
<https://about.me/sankarshan.mukhopadhyay>
_______________________________________________
Gluster-devel mailing list
Gluster-devel@gluster.org
http://www.gluster.org/mailman/listinfo/gluster-devel

Reply via email to