On 05/31/2018 09:22 AM, Shyam Ranganathan wrote:
> As brick-mux tests were failing (and still are on master), this was
> holding up the release activity.
> 
> We now have a final fix [1] for the problem, and the situation has
> improved over a series of fixes and reverts on the 4.1 branch as well.
> 
> So we hope to branch RC0 today, and give a week for package and upgrade
> testing, before getting to GA. The revised calendar stands as follows,
> 
> - RC0 Tagging: 31st May, 2018
> - RC0 Builds: 1st June, 2018
> - June 4th-8th: RC0 testing
> - June 8th: GA readiness callout
> - June 11th: GA tagging

GA has been tagged today, and is off to packaging.

> - +2-4 days release announcement

_______________________________________________
Gluster-devel mailing list
Gluster-devel@gluster.org
http://lists.gluster.org/mailman/listinfo/gluster-devel

Reply via email to