On 3 April 2012 21:59, Daniel Espinosa <[email protected]> wrote: > I'll review some bug reports regarding Vala/GObject Introspection, I'll > notify if I found some of them to be fixed before to release. I propose to > get release procedures like in GNOME, using Features/Code Freezes with > defined time frames between them as follows: > > a) State a Freeze for new features, may be starting today, > b) wait a week (up to April 10) to review bug reports to be fixed (no new > features must be added to fix them), then state Code Freeze status to wait > translators to finish > c) wait a week before release, may be on April 17
I agree on using that Features/Code Freezes before releases. However for the upcoming release, because I have some code I've been working on but not yet committed (LDAP write), I would like to start that process only after I commit that code, which might be in a few days. Vivien
_______________________________________________ gnome-db-list mailing list [email protected] http://mail.gnome.org/mailman/listinfo/gnome-db-list