I have a GoCD pipeline that looks like below:

 Stage 1: 
      Job 1:
         Task1 : Run tests for device 1
         Task2 : Run tests for device 2
         Task3 : Run tests for device 3

Issue is that we are running these tests remotely. And one of three devices 
fail at times due to remote devices not being available. Is it possible to 
disable a task in gocd if we know a device is going to be down for a whole 
day. Any ideas on this is welcome.

(I know this is a problem that needs to be fixed outside gocd, but the 
intention of the question is to understand if gocd gives this level of 
flexibility at all)

-- 