I have a GoCD pipeline that looks like below:
Stage 1:
Job 1:
Task1 : Run tests for device 1
Task2 : Run tests for device 2
Task3 : Run tests for device 3
Issue is that we are running these tests remotely. And one of three devices
fail at times due to remote devices not being available. Is it possible to
disable a task in gocd if we know a device is going to be down for a whole
day. Any ideas on this is welcome.
(I know this is a problem that needs to be fixed outside gocd, but the
intention of the question is to understand if gocd gives this level of
flexibility at all)
--
You received this message because you are subscribed to the Google Groups
"go-cd" group.
To unsubscribe from this group and stop receiving emails from it, send an email
to [email protected].
For more options, visit https://groups.google.com/d/optout.