Hi, I created simple gantt chart. The final task on the chart has no start or end date but has a duration of a few days and two dependencies. I would expect the start date to be calculated as finaltask.startdate = max(dep1.enddate, dep2.enddate) but instead it seems to be using something like finaltask.startdate = min(dep1.enddate, dep2.enddate). Can someone please advise?
You can see what I did here: https://jsfiddle.net/v8qyjq2g/ Regards, Mustafa -- You received this message because you are subscribed to the Google Groups "Google Visualization API" group. To unsubscribe from this group and stop receiving emails from it, send an email to [email protected]. To post to this group, send email to [email protected]. Visit this group at http://groups.google.com/group/google-visualization-api. For more options, visit https://groups.google.com/d/optout.