Hi,
I created simple gantt chart. The final task on the chart has no start or 
end date but has a duration of a few days and two dependencies. I would 
expect the start date to be calculated as finaltask.startdate = 
max(dep1.enddate, dep2.enddate) but instead it seems to be using something 
like finaltask.startdate = min(dep1.enddate, dep2.enddate). Can someone 
please advise? 

You can see what I did here:

https://jsfiddle.net/v8qyjq2g/

Regards,

Mustafa

-- 