On 28/03/17 08:03, Martin Landa wrote:
Hi,
2017-03-03 10:28 GMT+01:00 Markus Neteler <[email protected]>:
I ask myself the question of this schedule is appropriate for point
releases. Maybe 1 month between soft and hard freeze is a lot ?
I would agree. Two/three weeks could be enough... Ma
+1
do you agree to change it from 30 to 20 days or even 14 days [1]? Ma
+1 for 14 days.
Moritz
_______________________________________________
grass-dev mailing list
[email protected]
https://lists.osgeo.org/mailman/listinfo/grass-dev