http://www.firstpost.com/fwire/india-leaps-beyond-fukushima-begins-nuke-plant-construction-43114.html

India leaps beyond Fukushima, begins nuke plant construction

* <http://www.firstpost.com/author/hidden>*Jul 18, 2011

*Rawatbhata (Rajasthan):* Satisfied after a fresh look at the safety
measures at its nuclear plants in the backdrop of the Fukushima accident,
the Centre signalled a go-ahead to its nuclear programme with the start of
construction work of its 25th atomic power plant at Rawatbhata in Rajasthan.

The first pour of concrete for the 700 MW indigenous Pressurised Heavy Water
Reactor (PHWR), the seventh nuclear plant at the Rajasthan Atomic Power
Station (RAPS), took place in this bustling Rajasthan township, about 65 km
from Kota.

The first pour of concrete ceremony, which signals the beginning of the
construction of a nuclear plant, was attended by Atomic Energy Commission
Chairman Srikumar Banerjee and Nuclear Power Corp. of India Ltd (NPCIL)
Chairman Shreyans Kumar Jain.

Banerjee gave the command to pour the concrete by pressing the button on the
control panel of the concrete pressure pump. Soon after the M45 grade
concrete began pouring in the foundation of what would be the emergency core
cooling system of the new reactor building. The concrete is being poured at
the rate of 90 cubic metres per hour and at a controlled temperature of 19
degree Celsius. To monitor the temperature, ice is being mixed with the
concrete.

The 700 MW PHWR, designed by NPCIL by scaling up its 540 MW PHWRs under
operation at Tarapur since 2005, is expected to be completed in the next
five years.

Banerjee said, “The 540 MW PHWR at Tarapur was built by NPCIL in a record
time of four years and ten months. We will try to beat that record.”

RAPS already has six units of PHWRs, five of which are producing over 1180
MW, the largest from a single site. Construction for the seventh unit began
today and excavation work is currently on for the eighth unit, also a 700 MW
PHWR.

The NPCIL currently operates 20 nuclear power plants across six sites and
has an installed capacity of 4780 MW.

The Centre had given a financial sanction of Rs 24,000 crore in October 2009
for building four units of 700 MW of PHWRs — two each at Kakrapar and
Rawatbhata in Rajashtan.

Two 700 MW PHWRs each are expected to come up at Bargi in Madhya Pradesh and
Fatehabad in Haryana.

The NPCIL is building two 1,000 MW VVER type nuclear power plants at
Kudankulam and two 700 MW PHWRs at Kakrapar in Gujarat. Unit 1 and 2 at
Kudankulam are expected to be operational by August this year and May next
year respectively.

Both the 700 MW units at Kakrapar are expected to start producing power by
2015 end.

Besides the 20 operating and five under-construction reactors, the Bharatiya
Nabhikiya Vidyut Nigam is building a 500 MW prototype fast breeder reactor
at Kalpakkam.

With the progressive completion of the Kudankulam reactors and the four 700
MW PHWRs at Kakrapar and Rawatbhata, the installed nuclear power capacity of
NPCIL is expected to reach 9580 MW by 2016.

Questions were raised on safety of operating nuclear power plants after the
nuclear accident at Fukushima in Japan triggered by a tsunami after a nine
magnitude earthquake.

The NPCIL conducted a thorough review of all the nuclear power plants across
the country and found them to be safe. It is also incorporating additional
safety measures at various plant sites following the Fukushima accident in
March this year.

-- 
Peace Is Doable

-- 
You received this message because you are subscribed to the Google Groups 
"Green Youth Movement" group.
To post to this group, send an email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/greenyouth?hl=en-GB.

Reply via email to