*The World Nuclear Industry Status Report 2013 - Executive summary &
conclusions*

*Thursday 11 July 2013*



*Two years after the Fukushima disaster started unfolding on 11 March 2011,
its impact on the global nuclear industry has become increasingly visible.
Global electricity generation from nuclear plants dropped by a historic 7
percent in 2012, adding to the record drop of 4 percent in 2011. This World
Nuclear Industry Status Report 2013 (WNISR) provides a global overview of
the history, the current status and the trends of nuclear power programs
worldwide.*



This report looks at nuclear reactor units in operation and under
construction. Annex 1 provides 40 pages of detailed country-by-country
information. A specific chapter assesses the situation in potential
newcomer countries. For the second time, the report looks at the
credit-rating performance of some of the major nuclear companies and
utilities. A more detailed chapter on the development patterns of renewable
energies versus nuclear power is also included. Annex 6 provides an
overview table with key data on the world nuclear industry by country.

The 2013 edition of the World Nuclear Industry Status Report also includes
an update on nuclear economics as well as an overview of the status,
on-site and off-site, of the challenges triggered by the Fukushima
disaster. However, this report’s emphasis on recent post-Fukushima
developments should not obscure an important fact: as previous editions
(see www.WorldNuclearReport.org) detail, the world nuclear industry already
faced daunting challenges long before Fukushima, just as the U.S. nuclear
power industry had largely collapsed before the 1979 Three Mile Island
accident. The nuclear promoters’ invention that a global nuclear
renaissance was flourishing until 3/11 is equally false: Fukushima only
added to already grave problems, starting with poor economics.

The performance of the nuclear industry over the year from July 2012 to
July 2013 can be summed up as follows:

Operation and Construction Data

(1 July 2013)

Operation. There are 31 countries operating nuclear power plants in the
world. A total of 427 reactors have a combined installed capacity of 364
GWe. These figures assume the final shutdown of the ten reactors at
Fukushima-Daiichi and -Daini. It should be noted that as of 1 July 2013
only two (Ohi-3 and -4) of the 44 remaining Japanese reactors are operating
and their future is highly uncertain. In fact, even if four utilities are
expected to submit restart requests in July 2013, many observers believe
that a large share of the suspended Japanese units will likely never
restart.

The nuclear industry is in decline: The 427 operating reactors are 17 lower
than the peak in in 2002, while, the total installed capacity peaked in
2010 at 375 GWe before declining to the current level, which was last seen
a decade ago. Annual nuclear electricity generation reached a maximum in
2006 at 2,660 TWh, then dropped to 2,346 TWh in 2012 (down 7 percent
compared to 2011, down 12 percent from 2006). About three-quarters of this
decline is due to the situation in Japan, but 16 other countries, including
the top five nuclear generators, decreased their nuclear generation too.

The nuclear share in the world’s power generation declined steadily from a
historic peak of 17 percent in 1993 to about 10 percent in 2012. Nuclear
power’s share of global commercial primary energy production plunged to 4.5
percent, a level last seen in 1984. Only one country, the Czech Republic,
reached its record nuclear contribution to the electricity mix in
2012.Figure 1: Nuclear Electricity Generation in the World

*Age.* In the absence of major new-build programs, the unit-weighted
average age of the world nuclear reactor fleet continues to increase and in
mid-2013 stands at 28 years. Over 190 units (45 percent of total) have
operated for 30 years of which 44 have run for 40 years or more.

*Construction.* Fourteen countries currently are currently building nuclear
power plants, one more than a year ago as the United Arab Emirates (UAE)
started construction at Barrakah. The UAE is the first new country in 27
years to have started building a commercial nuclear power plant.

As of July 2013, 66 reactors are under construction (7 more than in July
2012) with a total capacity of 63 GW. The average construction time of the
units under construction, as of the end of 2012, is 8 years. However:

 • Nine reactors have been listed as “under construction” for more than 20
years and four additional reactors have been listed for 10 years or more.

• Forty-five projects do not have an official planned start-up date on the
International Atomic Energy Agency’s (IAEA) database.

• At least 23 have encountered construction delays, most of them
multi-year. For the remaining 43 reactor units, either construction began
within the past five years or they have not yet reached projected start-up
dates, making it difficult or impossible to assess whether they are on
schedule or not.

• Two-thirds (44) of the units under construction are located in three
countries: China, India and Russia.

The average construction time of the 34 units that started up in the world
between 2003 and July 2013 was 9.4 years.

 *Reactor Status and Nuclear Programs *

*• Startups and Shutdowns.* Only three reactors started up in 2012, while
six were shut down and in 2013 up to 1 July, only one started up, while
four shutdown decisions—all in the U.S.—were taken in the first half of
2013. Three of those four units faced costly repairs, but one, Kewaunee,
Wisconsin, was running well and had received a license renewal just two
years ago to operate up to a total of 60 years; it simply became uneconomic
to run. As of 1 July 2013, there were only two reactors operating in Japan
and how many others will receive permission to restart and over what
timeframe remains highly uncertain.

*• Newcomer Program Delays.* Engagement in nuclear programs has been
delayed by most of the potential newcomer countries, including Bangladesh,
Belarus, Jordan, Lithuania, Poland, Saudi Arabia and Vietnam.

 *Construction & New Build Issues *

*• Construction Cancellation.* In Russia, one reactor, which had just
started construction in 2012 (Baltic-1), was abandoned in May 2013.

*• Construction Starts.* In 2012, construction began on six reactors and on
three so far in 2013, including on two units in the U.S. for the first time
in three and a half decades. Those two units have been offered over $8
billion in federal loan guarantees and other subsidies whose total rivals
their construction cost, and special laws have transferred financial risks
to the taxpayers and customers.

*• Certification Delays.* The certification of new reactor designs has
continued to be delayed, in the U.S. certification of the
Franco-German-designed EPR was pushed back again, this time to 2015. Only
the Westinghouse AP1000 has received full generic design approval in the
U.S.

*• Construction Start Delays.* In various countries firmly planned
construction starts were delayed, most notably in China, where for almost
two years, between December 2010 and November 2012, not a single new
reactor building site was opened. Furthermore, in the first half of 2013 it
did not start any further constructions.

 *Economics & Finances *

*• Capital Cost Increases.* Construction costs are a key determinant of the
final nuclear electricity generating costs and many projects are
significantly over budget. Cost estimates have increased in the past decade
from $1,000 to $7,000 per kW installed. The U.S. Vogtle project, now
officially under construction, is built by the same firm whose two previous
reactors at that site were originally budgeted at $660 millionand were
later estimated to have cost $9 billion.

*• State Aid.* The U.K. model of Contract for Difference (CFD), a kind of
feed-in tariff agreement for nuclear electricity that is aimed at providing
a subsidy scheme for new-build, in the view of many observers, is likely to
violate current EU competition rules.

*• Operating Cost Increases.* In some countries, especially the U.S.
illustrated by the Kewaunee case, historically low inflation-adjusted
operating costs—especially for major repairs—have escalated so rapidly that
the average reactor’s operating costs is barely below the normal band of
wholesale power prices.

*• Post-Fukushima Costs.* Additional costs arising from upgrading and
backfitting measures following the lessons of the Fukushima crisis are only
beginning to surface. They are likely to have substantial impact on
investment as well as operational costs.

*• Income and Debt.* Nine out of 14 major utilities assessed saw their
earnings decline over the past five years while 13 constantly increased
their debt level.

*• Credit Rating.* Over the past five years, 15 assessed nuclear utilities,
10 were downgraded by credit rating agency Standard and Poor’s, four
companies remained stable, while only one was upgraded over the same
period. Rating agencies consider nuclear investment risky and the
abandoning of nuclear projects explicitly “credit positive”.

*• Share Value.* The share value of the world’s largest nuclear operator,
French state utility EDF, went down by 85 percent over the past five years,
while the share price of the world’s largest nuclear builder, French state
company AREVA, dropped by up to 88 percent.

 *Fukushima Status Report *

This assessment includes analyses of on-site and off-site challenges that
have arisen from the 3/11 disaster. To what extent the disaster was
triggered by the earthquake or the tsunami or by both in combination cannot
yet be conclusively elucidated.

*• On-site Challenges.* Radiation readings inside the reactor buildings of
units 1—3 vary between 5 mSv/h and 73 Sv/h, which makes human intervention
almost impossible. Massive amounts of water, about 360 tons per day, are
still pumped into the destroyed reactors via makeshift vinyl tubes that
frequently leak. This water, together with a similar additional amount of
groundwater, seeps into the basements of the reactor buildings, some of it
decontaminated to some degree and re-injected. The amount of radioactive
water that cannot be re-used is constantly increasing and has reached
380,000 tons in precarious storage of which 90,000 tons in the basements.
It is estimated that 27 times the amount of cesium-137 released into the
air in the first three weeks or more than 2.5 times the total amount
released at the Chernobyl accident is contained in this water.

*• Off-site Challenges.* More than 150,000 people remain in forced
evacuation. About 130,000 compensation claims have been filed. A total of
101 municipalities in 8 prefectures were designated as a “Scheduled
Contamination Survey Zone”, where annual doses between 1 and 20 mSv are
predicted and local authorities are responsible for decontamination work.
In addition, the central government is in charge of decontamination efforts
in 11 municipalities in Fukushima Prefecture covering 235 km2, where annual
doses exceed 20 mSv. Less than 5 percent of the surface has seen any
decontamination efforts.

The worst-case scenario, as depicted by the Chairman of the Japan Atomic
Energy Commission in the middle of the crisis in March 2011, remains the
collapse of the spent fuel pool of unit 4 and a subsequent fuel fire,
potentially requiring evacuation of up to 10 million people in a 250 km
radius of Fukushima, including a significant part of Tokyo.

* Nuclear Power vs. Renewable Energy Deployment *

In spite of a slight decrease in global investment in 2012, partly
reflecting rapidly falling equipment prices, renewable energy development
continues its rapid expansion in both, capacity and generation. China,
Germany and Japan, three of the world’s four largest economies, as well as
India, now generate more power from renewables than from nuclear power.

*• Investment.* Global investment in renewable energy totaled $268 billion
in 2012, down from $300 billion the previous year but still five times the
2004 amount. China increased spending by 20 percent to $65 billion and was
by far the largest investor. While some big investors (U.S., Germany,
Italy) reduced their spending considerably, some smaller players boosted
their investments and reached the top ten, including South Africa, which
skyrocketed spending by a factor of 200 to reach $5.5 billion, and Japan,
which added 75 percent to reach $16 billion.

*• Installed Capacity.* Globally, since 2000, the annual growth rates for
onshore wind power have averaged 27 percent and for solar photovoltaics 42
percent. This has resulted in 2012 in 45 GW of wind and 32 GW of solar
being installed, compared to a net addition of 1.2 GW of nuclear. China has
a total of 75 GW of operating wind power capacity, roughly doubled in each
of the past five years.

*• Electricity Generation.* In 2012 wind produced almost 500 TWh and solar
power about 100 TWh more than in 2000, while nuclear power generated 100
TWh less. For the first time in 2012 China and India generated more power
from wind than from nuclear plants, while in China solar electricity
generation grew by 400 percent in one year.



http://www.worldnuclearreport.org/Executive-summary-conclusions.html




-- 
Peace Is Doable

-- 
You received this message because you are subscribed to the Google Groups 
"Green Youth Movement" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send an email to [email protected].
Visit this group at http://groups.google.com/group/greenyouth.
For more options, visit https://groups.google.com/groups/opt_out.


Reply via email to