[Reproduced below are two (recent) news reports, at sl.no. I & 2, and
a (somewhat older) detailed analytical article highlighting some of
the problems and likely hazards, at sl. no. III.

At sl.no. I, a vendor's representative, being tagged as an "expert",
is describing the current problem as "minor." That a representative of
the vendor will try to categorise any and every problem, linked to the
vendor, as "minor", till it blows up in the face, is hardly any news.
What, however, is of interest is that the "expert" repeatedly refers
to the "pre-commissioning" operation  - which is long over, as if such
operation is anything extraordinary. Of cardinal relevance is,
however, the following:
"The unit was shut down for maintenance in July this year and was
restarted in September.
"The Kudankulam builders - ***Russia's nuclear energy corporation
Rosatom - said in a statement Wednesday that the unit shutdown Sep 26
followed certain deviations found in the "turbo-arlernator", and it
will resume operations by December***." [Emphasis added.]
Two things need be noted. One, even if the turbine has a different
manufacturer (understandably the Power Macines:
<http://www.netzwerkit.de/Members/MaxMoritz/news20130412-001> ), it is
the Rosatom, the main vendor for the nuclear reactor (see:
<http://www.power-technology.com/projects/kudankulam-nuclear-power-plant/>),
which is responsible. Two, after a month of shutdown, the vendor, in
the month of October, is reassuring that it's only a "minor" problem
and will "resume operations by December!"

The analytical article, by one who is very well supposed to know what
he is talking of, clearly shows that the plant is beset with technical
issues from the very word "go". (Mark the emphasised portions, in
particular.)
The construction of the Reactor I had commenced back in March 31 2002.
(Source: <http://globalenergyobservatory.org/geoid/44876>.) Supply of
sub-standard equipments and parts, by the sub-vendor ZiO-Podolsk in
particular, has always been a major issue.
Poor quality control appears to be a serious malaise.]

I/III.
http://www.business-standard.com/article/news-ians/minor-problem-stalls-kudankulam-no-safety-issues-expert-114102200888_1.html

Minor problem stalls Kudankulam, no safety issues: Expert
IANS  |  New Delhi
October 22, 2014 Last Updated at 20:02 IST

The first unit of the Russian built Kudankulam nuclear plant, which
stopped operations late last month after a minor malfunction in the
unit's turbine, will resume operations soon, a Russian expert said
Wednesday.

Commenting on an earlier IANS report, Alexander Uvarov of the
Moscow-based nuclear think tank Atominfo said the first unit was shut
down as per procedure during the pre-commissioning stage after some
minor problems were detected in the turbine.

"In the course of tests conducted during the pre-commissioning stage
some minor malfunctions of the turbine were seen. However all safety
systems activated reliably, the malfunction was diagnosed promptly and
repairs are being carried out," Uvarov told IANS over the phone.

"The pre-commissioning tests stage is purposed exactly to observe such
malfunctions. There are no danger or risks for population, environment
or sea," he added.

The unit was shut down for maintenance in July this year and was
restarted in September.

The Kudankulam builders - Russia's nuclear energy corporation Rosatom
- said in a statement Wednesday that the unit shutdown Sep 26 followed
certain deviations found in the "turbo-arlernator", and it will resume
operations by December.

"During operating period on Sep 26, the first power unit of Kudankulam
NPP faced 830 MW inclination of certain operating figures of the
turbo-alternator. The power unit will resume operation by this
December," Rosatom said.

The KNPP, located in Tirunelveli district of Tamil Nadu, is India's
first pressurised water reactor belonging to the light water reactor
category.

The first unit attained criticality July 2013, which is the beginning
of the fission process. The unit has started power generation and has
been connected to the southern grid.

(Biswajit Choudhury can be reached at [email protected])

II/III.
http://www.ndtv.com/article/south/unit-1-of-kudankulam-power-plant-shut-down-for-6-to-8-weeks-609553

Unit 1 of Kudankulam Power Plant Shut Down for 6 to 8 Weeks
South | Indo-Asian News Service | Updated: October 20, 2014 22:34 IST


Unit 1 of Kudankulam Power Plant Shut Down for 6 to 8 Weeks
Chennai:  A major problem in the first atomic power unit's turbine at
Kudankulam has put the unit out of action for around six-eight weeks,
the Nuclear Power Corporation of India Ltd (NPCIL) said on Monday.

"The unit has been shut down to inspect turbine and its associated
components before putting it for commercial operation. Maintenance
activities are in progress before the Unit is expected to be back in
service, some components of turbine needs replacement,for which action
has been initiated," RS Sundar, site director, Kudankulam Nuclear
Power Project, said in a statement.

According to him, the first unit is expected to be back in service by
six-to-eight weeks time.

"The turbine of the first unit has developed some problem. It seems
some component inside the turbine turned loose and damaged the turbine
blades," the source told IANS preferring anonymity.

According to him, discussions are on with the experts on whether to
replace the faulty equipment from the turbine of the second unit so
that the first unit could be run at the earliest.

The first unit stopped operations on September 26 due to turbine problem.

The unit was shut down for maintenance in July this year and was
restarted in September.

However, senior officials of NPCIL were not available for
clarifications on how the components would be replaced importing from
Russia or taking them out of the second unit's turbine.

Speaking to IANS, G Sundarrajan, an anti-nulcear power activist who
has filed a case against KNPP in the Supreme Court questioning the
safety, said, "Even before starting its commercial operations the
world class third generation plant is on the blink."

Atomic power plant operator NPCIL is setting up two 1,000 MW Russian
reactors at Kudankulam in Tirunelveli district, 650 km from Chennai.
The total outlay for the project is over Rs.17,000 crore.

The KNPP is India's first pressurised water reactor belonging to the
light water reactor category.

The first unit attained criticality on July 2013, which is the
beginning of the fission process. The unit has started power
generation and has been connected to the southern grid.

Work on commissioning the second unit is in progress. The unit is
expected to start the fission process next month.

Story First Published: October 20, 2014 16:29 IST

III.
http://www.newindianexpress.com/columns/Resolve-Koodankulam-issues/2013/04/19/article1551164.ece

Resolve Koodankulam issues

By A Gopalakrishnan

Published: 19th April 2013 07:36 AM
Last Updated: 19th April 2013 07:36 AM

The  first of the two 1000 MWe  VVER  nuclear reactors  at
Koodankulam Project (KKNP-1), under  commissioning and  testing , is
supplied  by  the  Russian atomic energy corporation, Rosatom ,through
its subsidiary, Atomstroyexport. On the Indian side , the KKNP project
is owned by the Nuclear Power Corporation of India Limited (NPCIL) , a
public sector undertaking of the Department of Atomic Energy (DAE) .
The overall safety regulation responsibility is with the Atomic Energy
Regulatory Board (AERB) .

Crucial  materials and  reactor parts have been exported to KKNP-1 & 2
 by  a  Russian government-owned company called  Machine-Building
Plant ZiO-Podolsk (ZiO) , which is another Rosatom subsidiary.
***ZiO-Podolsk*** (emphasis added) supplies have been sent for years
to all the Russian nuclear power plants, and to most of the VVER
plants exported to countries like India, Iran, China and Bulgaria.
These include  important safety subsystems , equipment , components
and materials supplied over the years to KKNP-1 & 2 .

***KKNP-1 was originally scheduled to start operation in early 2010 ,
but presently even the final start-up testing is not completed . In
January 2013 , the Secretary, DAE, stated that he was totally certain
that the reactor would be started that month itself, but it did not
happen.*** [Emphasis added.]

***From  NPCIL's continuing inability to start-up  KKNP-1  till now ,
it is very obvious that the Indo-Russian commissioning team at
Koodankulam is facing some serious problems which they never
anticipated.*** [Emphasis added.]

The congenital lack of transparency from which the Prime Minister's
Office (PMO) and the nuclear sector organisations are suffering always
prevents the public from knowing the real story. ***The DAE
Secretary's reasons for the delay in KKNP-1 start-up is  that " the
engineers have opened up a few of the valves and such components for
maintenance and it's taking some time." M.R Srinivasan, Member (AEC),
is reported to have said, "We sought an additional safety mechanism ,
which consists of valves. The original reactor design had to be
altered and I believe this is the basic cause for delay . The valves
were designed partially in India and Russia and compatibility with the
reactor led to some hiccups."*** [Emphasis added.]

***The fact that a  high-cost , high-risk  nuclear reactor is facing
defects and deficiencies in its components and equipment even before
it is  started up is highly unusual, and this  indicates  gross
failures  at several levels in the DAE-AERB-NPCIL-Atomstroyexport
combine.*** [Emphasis added.]

 ***If designs have been checked and followed , procurement of
materials  and fabrication have been done as per technical
specifications, testing and quality control at the manufacturer's
shops were comprehensive, and NPCIL's Quality Assurance (QA) before
acceptance of supplies at site were strictly as per nuclear norms,
these problems could not have arisen at the commissioning stage.***
[Emphasis added.]

 If news trickling out of KKNP-1 site is to be trusted, ***the Russian
special check valves in the passive long-term core flooding system
(hydroaccumulator system- stage 2) are defective as received and, at
this late hour an order to manufacture one or more such valves has
been placed on a reputed Hyderabad company. One or more of the new
Russian valves show cracks even at the finish of initial commissioning
tests. Similarly, the passive heat removal system (PHRS) is not
functioning as per specifications, because the damper -- air heat
exchanger --  vane system has not been integrally tested at the Russian
manufaturer's works as required and problems were not sorted out there
itself.*** [Emphasis added.] There are other problems to list, but the
above are typical of the   flaws holding up the reactor commissioning.
***Almost all these malfunctioning components and sub-systems have
been produced by ZiO-Podolsk*** (emphasis added), and all of them are
crucial to the safety of  the plant, under beyond-design-basis
accidents.

The Bellona Foundation, an international environmental NGO based in Norway

(http://www.bellona.org/), stated
(http://www.anti-atom.ru/en/node/3468 ) in February 2012 that ***the
Russian Federal Security Service (FSB) had arrested Sergei Shutov, the
procurement director of ZiO-Podolsk, on charges of corruption and
fraud. The FSB has charged Shutov with buying low-quality raw
materials on the cheap over the years, passing them off as
high-quality materials, and pocketing the difference***. [Emphasis
added.]

It is not clear how many reactors have been impacted by this alleged
crime, but ***reactors built by Russia in India, Bulgaria, Iran and
China are among those suspected to have received sub-standard
equipment and components*** (emphasis added), given the timeframe of
work completed.

 Bulgaria has already asked Atomstroyexport and ZiO-Podolsk to provide
details of materials used in their reactors, including quality
certificates. Similarly , China's Tianwan plant has two VVER-1000
reactors, and the Chinese have raised several hundred queries
regarding the low quality of materials and components.

 ***Investigative Journalists, an NGO based in the Armenian capital,
has said 
(http://hetq.am/eng/news/11194/russian-prosecutors-arrest-state-nuclear-official.html
) that the use of substandard materials could lead to a nuclear
disaster. "Stopping and conducting full scale checks of reactors where
equipment from ZiO-Podolsk has been installed is absolutely
necessary," Vladimir Slivyak, co-chair of Russian environmental NGO
Ecodefence, said recently."Otherwise the risk of a serious accident at
a nuclear power plant, whose clean-up bill, stretching into the tens
and even hundreds of millions of dollars, will have to be footed by
taxpayers."*** [Emphasis added.]

***The problems with ZiO-Podolsk supplies to the  KKNP-1 Project, seen
in the context of the widespread allegations of corruption and poor
quality, indicate that the root cause of KKNP-1 problems lies in those
sub-standard supplies*** (emphasis added). Recent questions raised
under RTI to the AERB and NPCIL resulted only in evasive and pointless
replies. Asked about parts supplied by ZiO, AERB says "the selection
of a company for supplying any equipment to NPCIL is not under the
purview of AERB." For the same query, NPCIL says, "No information
regarding any investigation against ZiO-Podolsk is available to
NPCIL". Both these DAE organisations were lying in these replies, as
is evident from the following facts.

The website of the Russian Embassy in India carries the news of a
senior Indian delegation
(http://www.rusembassy.in/index.php?option=com_content&view=
article&id=4881%3A-q-q&catid=10%3A2010-01-21-11-06-46&lang=ru ) headed
by  AP Joshi, Special Secretary, DAE  having visited ZiO-Podolsk from
July 15-18, 2012, just about five months after the arrest of Sergei
Shutov, Zio-Podolsk's  Procurement Director, for fraud and corruption
in sending out inferior products to national and foreign reactor
projects , including KKNP-1 & 2.

The Indian Embassy in Moscow and the NPCIL / DAE personnel stationed
there must  have  certainly known  about  Shutov's arrest , and  the
inherent serious implications of his actions on the safety of KKNP-1 &
2. They would have  briefed the DAE Secretary  about it immediately
and through him the PMO would also have been alerted . And yet , both
AERB and NPCIL pretend  to take the ZiO-Podolsk matter very lightly
and feign ignorance .

***One can only surmise that the PMO & the DAE quickly realied  the
gravity of the potentially explosive situation that could develop
vis-a-vis Koodankulam reactor safety, following Shutov's arrest,
because by then several crucial equipment, components and materials
with alleged poor quality and deficiencies have been already installed
in various parts of both units at KKNP and Unit-1 was on its way to
commissioning. The PMO & DAE seem to have decided to weather the storm
through the joint execution of an Indo-Russian cover-up plan, and hold
a firm position that all is well with KKNP supplies.*** [Emphasis
added.]

After a fire-fighting strategy was framed in India , it would appear
that the PMO despatched the Special Secretary, DAE, and his team to
visit ZiO-Podolsk and spent three days to firm up the modus operandi
of tackling the rather tricky situation which could develop in India
once the protesters and the courts of law come to know of the scam
details. After all , the PMO's top priority is to meet  the PM's
promise to President Putin that KKNP-1 will be started up in April
2013, and public safety and corruption come only after that .

There could be a large number of equipment, components and materials
of substandard quality from ZiO-Podolsk  already installed in various
parts of KKNP- 1 & 2  whose deficiencies and  defects are dormant
today, but these very same shortcomings may cause such parts to
catastrophically fail when the reactor is operated for some time .

Many such parts and materials may have been installed within the
reactor pressure vessel itself, which is now closed and sealed in
preparation for the start-up. Once the reactor is made critical and
reaches power operation, much of these components and materials inside
will become radioactive and/or will be in environments where they
cannot be properly tested for quality or performance.

Under the circumstances , KKNP Unit-1 commissioning and  KKNP-2
construction work must be stopped forthwith, and there can be no
question of resuming these works towards start-up of both these
reactors until a thorough and impartial investigation is carried out
into the impact of this corruption scandal and sub-standard supplies
on the safety of these reactors.

 And these investigations must be carried out by a team, where
majority membership  must  not  be  from  DAE , NPCIL and AERB, but
include subject experts from other organisations in the country.

India must also seriously consider inviting an IAEA expert team
specially constituted to investigate the specific issues which this
scandal has thrown up.

***Gopalakrishnan is a former Chairman of India's Atomic Energy
Regulatory Board*** [Emphasis added.]

-- 
Peace Is Doable

-- 
You received this message because you are subscribed to the Google Groups 
"Green Youth Movement" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send an email to [email protected].
Visit this group at http://groups.google.com/group/greenyouth.
For more options, visit https://groups.google.com/d/optout.

Reply via email to