http://www.wsj.com/articles/areva-finds-flaws-in-new-nuclear-reactor-1428408394

EUROPEAN BUSINESS NEWS
Areva Finds Flaws in New Nuclear Reactor

French nuclear project has suffered big delays and cost overruns
The construction site of the Pressurized Water Reactor in Flamanville,
France, in February 2014. The project has suffered big delays and cost
overruns. ENLARGE
The construction site of the Pressurized Water Reactor in Flamanville,
France, in February 2014. The project has suffered big delays and cost
overruns. PHOTO: AGENCE FRANCE-PRESSE/GETTY IMAGES
By INTI LANDAURO
Updated April 7, 2015 9:39 a.m. ET

PARIS--French nuclear engineering firm Areva SA discovered flawed steel
in a crucial part of the nuclear reactor it is building in
Flamanville, northern France, the country's nuclear safety regulator
said Tuesday.

The announcement is a further blow for Areva as it struggles to stay
afloat after reporting four consecutive annual losses caused by bad
investment decisions, costly delays in the construction of reactors
such as the one at Flamanville and another in Finland.

The company has also been hurt by changing international attitudes
toward nuclear power, especially following the 2011 Fukushima disaster
in Japan.

Areva will carry out further tests on the reactor this month after
finding that steel in its vessel, which is designed to contain the
nuclear reactor, showed high carbon content, leading to lower
mechanical strength. The vessel has already been installed on the
site, according to a spokesman for state-controlled power utility
Electricité de France SA, which commissioned the reactor.

The results of those tests will be released in October, French Energy
Minister Segolene Royal said.

The construction site of the reactor in Flamanville, France, on
November 6, 2014. ENLARGE
The construction site of the reactor in Flamanville, France, on
November 6, 2014. PHOTO: CHARLY TRIBALLEAU/AGENCE FRANCE-PRESSE/GETTY
IMAGES
The French government, which controls more than 85% of Areva, is
considering merging parts of the company with its main client, the
power utility Electricite de France SA.

Areva is building the Flamanville reactor for EDF. It had already
suffered a series of incidents that led the two companies to delay its
completion by more than three years to 2017.

EDF recently estimated that its construction costs had skyrocketed to
EURO 8 billion ($8.7 billion) from an original estimate of EURO 3.3 billion.

The French regulator said it would forward the report on the vessel's
flaws to countries with similar projects.

Areva is currently building a reactor of the same design in Olkiluoto,
Finland. That too is also suffering massive delays and cost overruns.

An Areva spokeswoman said the vessel is installed in the Finland
project and that the country's regulator has approved the parts there.

II.
http://www.power-technology.com/news/newsareva-finds-flawed-steel-in-reactor-vessel-of-nuclear-plant-in-france-4549065

Areva finds flawed steel in reactor vessel of nuclear plant in France
8 April 2015

Areva has found weaker steel in a key part of the reactor vessel of a
nuclear plant that it is building in Normandy, France.

The Flamanville European Pressurised Reactor's (EPR) is being built
for EDF. Its completion is delayed by over three years to 2017 as
Areva suffered a series of incidents.

The costs involved in the construction of the EPR have increased from
the initial estimate of EURO 3.3bn to EURO 8bn.

When completed, the 1,650MW EPR reactor will contain atomic fuel and
prevent radioactivity escaping, according to the French Nuclear Safety
Authority (ASN).

"The costs involved in the construction of the EPR have increased from
the initial estimate of EURO 3.3bn to EURO 8bn."

During chemical and mechanical tests in a vessel similar to the one
installed in Normandy, manufacturing anomalies were found.

Upon completion of the initial tests, Areva found that one of the
criteria was not met in an area with greater than average carbon
content.

EDF and Areva are working to perform additional tests on the EPR as
soon as possible, following approval by the ASN on the test
conditions, and to provide the safety authority with all the necessary
information to demonstrate the safety and quality of the corresponding
equipment.

According to ASN, Chinese and Finnish regulators have been warned
after the discovery of weaker steel as Areva is developing an EPR in
Finland and EDF is working with Chinese companies to develop two at
Taishan in China.

Image: Computer designed picture of the planned European Pressurized
Water Reactor (EPR). Photo: courtesy of Framatome ANP / Wikipedia.

-- 
Peace Is Doable

-- 
You received this message because you are subscribed to the Google Groups 
"Green Youth Movement" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send an email to [email protected].
Visit this group at http://groups.google.com/group/greenyouth.
For more options, visit https://groups.google.com/d/optout.

Reply via email to