[《The cost of Olkiluoto 3 was initially estimated at 3.2 billion euros but
Areva in 2012 estimated the overall cost at closer to 8.5 billion euros.
Since then it has not updated its cost projection.
EDF on Monday confirmed a 10.5 billion euro cost estimate for a similar
European Pressurised Reactor (EPR) it is building in Flamanville, France,
which has suffered similar delays and cost overruns.》]

https://www.cnbc.com/2017/10/09/reuters-america-update-1-arevas-finland-nuclear-reactor-delayed-again-tvo-says.html

UPDATE 1-Areva's Finland nuclear reactor delayed again, TVO says

Published 4:22 AM ET Mon, 9 Oct 2017
Reuters
(Adds Areva comment, detail, background)

HELSINKI, Oct 9 (Reuters) - The start of regular power production at
Finland's biggest nuclear reactor Olkiluoto 3 will be delayed further until
May 2019, almost a decade later than originally planned, owner Teollisuuden
Voima (TVO) said on Monday.

The project in western Finland, built by a consortium led by French
state-owned nuclear group Areva, has been hit by repeated delays, soaring
costs and court disputes. Most recently, it had targeted the start of
regular power production for the end of 2018.

TVO said many important tests at the plant were yet to be carried out and
that Areva needed to allocate the necessary resources to the project.

"We are very disappointed by this additional delay. There is still
substantial work to be accomplished in the project," TVO project director
Jouni Silvennoinen said in a statement.

An Areva spokesman said the reactor would produce its first power at the
end of 2018, but that it would take four months to ramp up to full
production capacity, which would delay the commercial startup by four
months to May 2019.

He said hot-testing would start in December 2017, nuclear fuel would be
loaded in August 2018, first grid connection would be in December 2018 and
the commercial start would be May 2019.

Last month, TVO filed an appeal to the European Commission over France's
restructuring of its nuclear industry, saying Areva, which is selling its
nuclear reactor business to utility EDF, could be unable to meet its
liabilities in Finland.

The parties are locked in a dispute at the International Chamber of
Commerce, where TVO is claiming 2.6 billion euros from the Areva-led
consortium, which has filed a counter-claim of 3.6 billion euros. Areva has
a 73 percent stake in the consortium and Germany's Siemens 27 percent.

The cost of Olkiluoto 3 was initially estimated at 3.2 billion euros but
Areva in 2012 estimated the overall cost at closer to 8.5 billion euros.
Since then it has not updated its cost projection.

EDF on Monday confirmed a 10.5 billion euro cost estimate for a similar
European Pressurised Reactor (EPR) it is building in Flamanville, France,
which has suffered similar delays and cost overruns.

TVO's owners include Finnish paper companies UPM and Stora Enso as well as
utility Fortum.

($1 = 0.8344 euros) (Reporting by Jussi Rosendahl and Tuomas Forsell in
Helsinki and Geert De Clercq in Paris; Editing by Jason Neely and Mark
Potter)


-- 
Peace Is Doable

-- 
You received this message because you are subscribed to the Google Groups 
"Green Youth Movement" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send an email to [email protected].
Visit this group at https://groups.google.com/group/greenyouth.
For more options, visit https://groups.google.com/d/optout.

Reply via email to