I've had a similar issue with a small cluster. Is there any way that you can reduce the size of the data being joined on both sides? If you search the forums for join issue, you will see the thread for my issue and get some tips.

Thanks,
Ryan



On Nov 3, 2009, at 10:45 PM, Defenestrator <[email protected]> wrote:

I was able to increase the number of reduce jobs manually to 32. However, it finishes 28 of them and the other 4 has the same behavior of using 100% cpu and consuming a lot of memory. I'm suspecting that it might be an issue with the reduce job itself - is there a way to figure out what these jobs are doing exactly?

Thanks.

On Tue, Nov 3, 2009 at 6:53 PM, Namit Jain <[email protected]> wrote:
The number of reducers are inferred from the input data size. But, you can always overwrite it by setting mapred.reduce.tasks







From: Defenestrator [mailto:[email protected]]
Sent: Tuesday, November 03, 2009 6:46 PM


To: [email protected]
Subject: Re: Self join problem


Hi Namit,



Thanks for your suggestion.



I tried changing the query as you had suggested by moving the m1.dt = m2.dt to the on clause. It increased the number of reduce jobs to 2. So now there are two processes running on two nodes at 100% consuming a lot of memory. Is there a reason why hive doesn't spawn more reduce jobs for this query?



On Tue, Nov 3, 2009 at 4:47 PM, Namit Jain <[email protected]> wrote:

Get the join condition in the on condition:



insert overwrite table foo1

select m1.id as id_1, m2.id as id_2, count(1), m1.dt

from m1 join m2 on m1.dt=m2.dt where m1.id <> m2.id and m1.id < m2.id group by m1.id, m2.id, m1.dt;







From: Defenestrator [mailto:[email protected]]
Sent: Tuesday, November 03, 2009 4:44 PM
To: [email protected]
Subject: Self join problem



Hello,



I'm trying to run the following query where m1 and m2 have the same data (>29M rows) on a 3-node hadoop cluster. I'm essentially trying to do a self join. It ends up running 269 map jobs and 1 reduce job. The map jobs complete but the reduce job just runs on one process on one of the hadoop nodes at 100% cpu utilization and just slowly increases in memory consumption. The reduce job never goes beyond 82% complete despite letting it run for a day.



I am running on 0.5.0 based on this morning's trunk.



insert overwrite table foo1

select m1.id as id_1, m2.id as id_2, count(1), m1.dt

from m1 join m2 where m1.id <> m2.id and m1.id < m2.id and m1.dt = m2.dt group by m1.id, m2.id, m1.dt;