---------- Forwarded message ----------
From: Vimal Bhai <[email protected]>
Date: Thu, Sep 22, 2011 at 5:37 PM
Subject: Urgent Press Note: State should take decision on filling the Tehri
Dam Reservoir
To:

 *Matu Peoples' Organisation *

Delhi contact: D 334/10, Ganesh Nagar, Pandav Nagar Complex Delhi-110092
Blog<matujan.blogspot.com>

Contact Nor.: 09891814707

Press
Note
22-9-2011

*Project Name:* Tehri Dam HEP (1000 MW)

*Rivers:* Bhagirathi & Bhilangna

*Agency:* Tehri Hydro Development Corporation *(THDC)*

*Environmental Clearance granted on* 19-7-1990

*Dam Commission-*2006

*Tehri Dam case in Supreme Court:-* *N. D. Jayal & another vs. Union of
India & Others  (SLP (c) No. 22894 of 2005)*

**

*State should take decision on filling the Tehri Dam Reservoir
*

*Supreme Court of India says*


 The case pertaining to Rehabilitation & Resettlement (R/R) of persons
affected due to Tehri Dam and also on rise in water level above 830 Mts. in
the reservoir was heard by a Bench of the Supreme Court, consisting of
Justice R.V. Raveendran, Justice H.L. Gokhale & Justice A.K. Patnaik. The
Expert Committee constituted by State of Uttarakhand, pursuant to SC
direction has pointed out that due to raise in water level in the reservoir
up to 830 Mts. 27 villages were affected. These affected villages are
required to be considered for R/R. The petitioners N.D. Jayal and Shekhar
Singh, represented by Counsel Mr. Sanjay Parikh had argued on the last date
of hearing that villages affected due to landslide caused because of raise
in water level in the reservoir, are required to rehabilitated as per the
Tehri dam project rehabilitation policy, and not according to “Collateral
damage policy”.

 It may be stated that Rehabilitation has not been done according to
environment clearance dated 19/07/1990 and according to Hon’ble Supreme
Court judgment dated 1st September 2003. He said that 45 villages were
affected due to change in Rim Demarcation line are also in need of
rehabilitation according to R/R policy of the Tehri Dam. The work of the
rehabilitation sites is still incomplete even according to the Sub Committee
of the State of Uttarakhand. Land Rights have still not been given to the
oustees. There are 3 incomplete bridges in the Cut-off areas. Adv. Colin
Gonsalves counsel for the other petition for the R/R only also said that
rehabilitation has not been completed up to the mark.

 Mr Rawal, Additional Solicitor General (ASG) appearing for THDC started
arguing on raising the water level of Tehri Dam reservoir up to 830 Mts. The
Court pointed out that R/R of those affected up to 830 Mts, has still not
been done. When the ASG insisted on his prayer to raise the water level,
Justice Raveendran remarked that it can consider such prayer only on hearing
the entire case to satisfy themselves that R/R has

been done. When ASG continued pressing his argument, then Justice Patnaik
said “You want to produce electricity to run the ACs in Delhi but do not
consider R/R of the affected person important. We are here to protect the
Art 21 of the Constitution of India i.e. the Right to Life of the persons.

The Court referred to the previous orders by the SC, in which it was said
that THDC and State Government should sit together and finalise the R/R
issues, and he felt bad that even on recording of the parties differ.

The ASG told the Court that Tehri Hydro Electric Project & generation of
electricity is in the public interest, on that the Counsel of the
Petitioners, Mr. Sanjay Parikh countered it by saying that the R/R should
have been done much earlier than raising water level in reservoir, the
Public Interest is to protect the People’s Life and ensuring them R/R & not
the generation of electricity.

 The Court remarked that, the court is meant to protect Art 21 and State
should take care of Power (Generation of electricity). The Court directed
that the matter will be heard finally on a non – misc. day in November 2011
and meanwhile the State of Uttarkhand can decide on the THDC’s demand to
raise the water level.

 Counsel for the UKD Rachna Srivastava pointed out that when the required
money for R/R has not been given by THDC, then where is the question of
actual R/R of the people?


So now, the ball is in the court of the State of Uttarakhand. The State
government has to decide whether they want to submerge their own people
without R/R or to protect their life. Hence, the SC has put the burden of
decision making of this issue on both the State and Central Government.

 We hope the tussle going on between the State and Central Governments
should be stopped. The Central Government through its counsel ASG Rawal, has
declared that they have completed the R/R time to time. So now total
responsibility of protecting people’s lives is on the shoulders of State
Government.


 We, Matu Jansangathan, demand from State Government of Uttarkhand under the
view of the SC, that

   - they should not give permission to THDC for filling the reservoir
   according to demand which is just for the hunger of more power.


   - State Government should go for rehabilitation of the people up to 840
   mts. and above, affected due to the filling of the reservoir by one
   rehabilitation policy which is Tehri Dam Rehabilitation Policy.


 Vimalbhai

Convenor

(Was in the Supreme Court of India at the time of hearing)

Puran Singh

-- 
You received this message because you are subscribed to the Google Groups 
"humanrights movement" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/humanrights-movement?hl=en.

Reply via email to