We have over 30 LPARs in the same physical location. Some are running EST, 4 are running CST and 1 is running JST (Japan time). Our management made the decision that all times in the change records will be EST. So, if a change is scheduled for 3:00 am EST and is supposed to happen on a CST LPAR, the change happens at 2:00 CST, 3:00 EST.

Mark T. Regan, K8MTR wrote:
I'm thinking that too, but I was wondering if anyone else had encountered this 
issue too? I'm sure people have, due to all the data center consolations that 
have taken place.


----------------------------------------------------------------------
For IBM-MAIN subscribe / signoff / archive access instructions,
send email to [EMAIL PROTECTED] with the message: GET IBM-MAIN INFO
Search the archives at http://bama.ua.edu/archives/ibm-main.html

Reply via email to