Hi Jack
------------------------------ MODIFYING A RULE -------------------------------
.
Command ===>
.
.
Enter the GENDAYS command to display the dates generated by this rule
.
Enter the E command to specify EVERY options
.
Enter S and user data in the fields below to define a rule
.
.
Application : TEST
.
Rule : R1
.
.
--- Frequency --- --- Day --- --- Cycle Specification ---
.
-------------------------------------------------------------------------------
.
S Only ! _ Day ! _ Week _ January _ July
.
_ Every ! _ Free day ! S Month _ February _ August
.
! _ Work day ! _ Year _ March _ September
.
_ First _ Last ! _ Monday ! _ April _ October
.
S Second _ 2nd Last ! _ Tuesday ! _ May _ November
.
_ Third _ 3rd Last ! _ Wednesday ! _ June _ December
.
_ Fourth _ 4th Last ! _ Thursday ! Week number __ __ __ __ __ __
.
_ Fifth _ 5th Last ! _ Friday ! Period/RG ________ ________
.
___ ___ ___ ___ ! S Saturday ! name ________ ________
.
___ ___ ___ ___ ! _ Sunday !
.
___ ___ ___ ___ ! ! Shift default origin by ___ days
.
And
--------------------------------- RUN CYCLES ----------------- Row 1 to 1 of 1
Command ===> Scroll ===> CSR
Enter/Change data in the rows, and/or enter any of the following
row commands:
I(nn) - Insert, R(nn),RR(nn) - Repeat, D(nn),DD - Delete
S - Specify run days/Modify rule
Application : TEST
Name of rg/ In Out of
Row period/rule Input Deadline F day effect Effect Variable table
cmd HH.MM day HH.MM Type rule CCYYMMDD CCYYMMDD
'''' R1______ 10.00 __ _____ R 3 20210725 20711231 ________________
Text : __________________________________________________
Shift: __-4 Shift Day Type: D
The LTP gives the following date
06 sept 22
04 oct 22
08 nov 22
06 dec 22
Good luck
Philippe
> Le 23 août 2022 à 18:05, Jack Zukt <[email protected]> a écrit :
>
> Hi all,
>
> I need to execute a job every Thursday that takes place before the second
> Saturday of each month which, unfortunately, is not the second Thursday of
> each month. Is there a way to do this using IWS? From what I have gathered
> so far, I can only use relative days for a future date, not for a previous
> one.
> Your help will be greatly appreciated.
> Regards
> Jack
>
> ----------------------------------------------------------------------
> For IBM-MAIN subscribe / signoff / archive access instructions,
> send email to [email protected] with the message: INFO IBM-MAIN
----------------------------------------------------------------------
For IBM-MAIN subscribe / signoff / archive access instructions,
send email to [email protected] with the message: INFO IBM-MAIN