So a few options.

Buy product from DTS Software called SRS/ACC  - easy control through these 
products

If ALL users, then ACS code or ALLOCxx
If Some users, then maybe an Allocation Exit.

Lizette


-----Original Message-----
>From: Binyamin Dissen <[email protected]>
>Sent: Jul 2, 2015 11:34 AM
>To: [email protected]
>Subject: Re: IGW01184W SECONDARY EXTENT QUANTITY TEMPORARILY SET TO ONE
>
>On Thu, 2 Jul 2015 13:14:05 -0500 Mike Schwab <[email protected]> wrote:
>
>:>http://www-01.ibm.com/support/knowledgecenter/SSLTBW_2.1.0/com.ibm.zos.v2r1.ieam900/bv1184w.htm
>
>Yes, I recognize that is the "normal" behavior. I do not want it.
>
>:>>When the secondary extent is specified as zero for a PDS to PDSE copy, the 
>secondary extent is set to one unit of the space unit that is specified as the 
>primary allocation, to allow the copy to proceed. A PDSE is likely to run 
>slightly larger than a PDS, and the user might not have allocated the PDSE any 
>larger. At the end of processing, the secondary extent is set back to zero.
>
>:>On Thu, Jul 2, 2015 at 12:58 PM, Binyamin Dissen
>:><[email protected]> wrote:
>:>> But I do not want it to be set/increased.
>
>:>> How can I force it so that secondary extents are not allocated?
>
>--
>Binyamin Dissen <[email protected]>
>http://www.dissensoftware.com
>
>Director, Dissen Software, Bar & Grill - Israel

----------------------------------------------------------------------