https://www.ibm.com/it-infrastructure/z/technologies/gdps

https://www.infoworld.com/article/2614033/disaster-recovery/data-centers-under-water--what--me-worry-.html

On Wed, Jan 3, 2018 at 12:18 AM, Alan(GMAIL)Watthey <[email protected]> wrote:
> I have had a strange request from management as to how far apart we can move
> our production systems.  I know there are limitations on how far the (in
> this case) two systems (and two coupling facilities) can be apart and I've
> dug up an old IBM Redbook on the issue where they did tests with a sysplex
> at 0, 20, 40, 60 and 80 kms apart.  Physical limitations (eg. FICON) don't
> seem to be an issue.  We are a CICS and DB2 shop so the manual certainly
> addressed issues that we might see but it is dated 2008 so has anything
> changed since then?  CICS and DB2 have moved on a long way in that time.
>
>
>
> I was thinking of saying up to 10km but this is really a finger in the air
> value.  Maybe it's only 5 and maybe its 20 or 30.  Can we just throw CPU and
> memory at it as I would think we would have a lot more transactions running
> at the same time with some (but not all apparently) having extra delays
> incurred?  The transaction increases suggested in that manual are
> milleseconds and these days (with all the distributed systems involved) the
> users are happy to get 10 second response times.  Admitted this can involve
> many, many transactions behind the scenes from the application servers to
> populate their crowded browser screens.  Gone are the days of data-entry
> pools and sub-second responses.
>
>
>
> What I was wondering is there anyone out there with real life experience on
> this kind of activity.  How far apart do people run their sysplex systems?
> What gotchas sprang up to relieve them of their sanity?  Any pointers would
> be gratefully appreciated.
>
>
>
> Regards,
>
> Alan Watthey
>
>
>
> From: IBM Mainframe Discussion List [mailto:[email protected]] On
> Behalf Of IBM-MAIN automatic digest system
> Sent: 03 January 2018 8:00 am
> To: [email protected]
> Subject: IBM-MAIN Digest - 1 Jan 2018 to 2 Jan 2018 (#2018-2)
>
>
>
>
>
>
> ----------------------------------------------------------------------
> For IBM-MAIN subscribe / signoff / archive access instructions,
> send email to [email protected] with the message: INFO IBM-MAIN



-- 
Mike A Schwab, Springfield IL USA
Where do Forest Rangers go to get away from it all?

----------------------------------------------------------------------
For IBM-MAIN subscribe / signoff / archive access instructions,
send email to [email protected] with the message: INFO IBM-MAIN

Reply via email to