Hi Pat,


This is the latest one that has been changed.

It is on the website  <https://wiki.iotivity.org/release_schedule_in_2015>
https://wiki.iotivity.org/release_schedule_in_2015

When anything to be changed, it will be on the website.



1.0.0 : ?OIC Spec 1.0 Compliant release?

?  Type for Release : Major release, Feature Driven, PlugFest #4

?  Schedule (6 weeks ahead of QA completion) (cf. Original QA request is 6
weeks ahead of QA start)

?  08/28, API freeze & Programmer?s guide freeze

?  09/18, Feature complete & Review Complete and make ?0.9.2-RC1?
release to QA

?  09/25, QA 1st round complete

?  10/02, QA 2nd round complete

?  10/09, QA 3rd round complete

?  10/12, Website Open

?  10/19 week, Plug Fest #4 (TBD)





June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair 

IoTivity Release Function Lead


Samsung Electronics Co.,Ltd.

Software R&D Center, IoT Solution Lab. | Web & Convergence Team

Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107

E-mail :juney at samsung.com



From: [email protected] [mailto:iotivity-dev-
bounces at lists.iotivity.org] On Behalf Of Lankswert, Patrick
Sent: Thursday, August 06, 2015 5:50 AM
To: iotivity-dev at lists.iotivity.org
Cc: Uzell, ChristopherX
Subject: [dev] Checking on date



June,



I wanted to check with you to make sure that the dates for 1.0 have not
changed. Your original email follows.



Pat



From: [email protected] [mailto:iotivity-dev-
bounces at lists.iotivity.org] On Behalf Of ???(June Yong Young)
Sent: Friday, June 12, 2015 4:48 AM
To: iotivity-dev at lists.iotivity.org
Subject: [dev] Release schedule announcement for IoTivity 0.9.2~1.0.0



Dear IoTivity members,



We have 3 more releases had been planned after 0.9.1.

And I suggest and announce the release schedule in advance that has been
confirmed in ISG, please have a look at this schedule and let us know your
opinion.



[PCL: 0.9.2 and 0.9.3 discussion removed]



3. 1.0.0 : ?OIC Spec 1.0 Compliant release?

- Type for Release : Major release, Feature Driven, PlugFest #4

- Schedule (6 weeks ahead of QA completion) (cf. Original QA request is 6
weeks ahead of QA start)

. 8/28, API freeze & Programmer?s guide freeze

. 9/18, Feature complete & Review Complete and make "0.9.2-RC1" release to
QA

. 9/25, QA 1st round complete

  . 10/02, QA 2nd round complete

. 10/09, QA 3rd round complete

. 10/12, Website Open 

. 10/19 week, Plug Fest #5(TBD)





cid:image001.png at 01D0D027.1B4D0A00







June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair 

IoTivity Release Function Lead


Samsung Electronics Co.,Ltd.

Software R&D Center, IoT Solution Lab. | Web & Convergence Team

Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107

E-mail :juney at samsung.com



-------------- next part --------------
An HTML attachment was scrubbed...
URL: 
<http://lists.iotivity.org/pipermail/iotivity-dev/attachments/20150806/376648bb/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 141666 bytes
Desc: not available
URL: 
<http://lists.iotivity.org/pipermail/iotivity-dev/attachments/20150806/376648bb/attachment.png>