Hi Pat, George, Jawid,

When will Intel?s QA complete 2nd round test?



Hi Pat, Jawid, SoonHwang,

Could you let us know the 2nd round test result by 7/31, so that we can find 
out whether or not we need RC3?





0.9.2 : ?Spec vA Compliant + Spec vB Partial?

?  Type for Release : Minor release, Schedule Driven, PlugFest #3

?  Schedule (5 weeks ahead of QA completion) (cf. Original QA request is 6 
weeks ahead of QA start)

?  6/22, API freeze & Programmer?s guide freeze

?  7/20, Feature complete & Review Complete and make ?0.9.2-RC1? release to QA

?  7/24, QA 1st round complete

?  7/27->7/28, 0.9.2-RC2 release to QA

?  7/31, QA 2nd round complete

?  8/03, Website Open (if no issue)

?  8/17 week, Plug Fest #3





June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair 

IoTivity Release Function Lead


Samsung Electronics Co.,Ltd.

Software R&D Center, IoT Solution Lab. | Web & Convergence Team

Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107

E-mail :juney at samsung.com



From: iotivity-dev-bounces at lists.iotivity.org 
[mailto:[email protected]] On Behalf Of ???(June Yong 
Young)
Sent: Wednesday, July 29, 2015 4:50 PM
To: 'Agrawal, Sachin'; '???'; Jawid Mirani_Intel; ?????; ?????_SE
Cc: iotivity-dev at lists.iotivity.org
Subject: Re: [dev] About preparing 0.9.2 Security Release



Hi Sachin,

Thank you for the tagging 0.9.2-RC2.



Hi Pat, George, Jawid,

I think still there is no more schedule delay required although RC2 has been 1 
day delayed.

However I am not sure what is Intel QA?s position about 7/31 QA 2nd round 
completion date although Samsung QA is positive.



0.9.2 : ?Spec vA Compliant + Spec vB Partial?

?  Type for Release : Minor release, Schedule Driven, PlugFest #3

?  Schedule (5 weeks ahead of QA completion) (cf. Original QA request is 6 
weeks ahead of QA start)

?  6/22, API freeze & Programmer?s guide freeze

?  7/20, Feature complete & Review Complete and make ?0.9.2-RC1? release to QA

?  7/24, QA 1st round complete

?  7/27->7/28, 0.9.2-RC2 release to QA

?  7/31, QA 2nd round complete

?  8/03, Website Open (if no issue)

?  8/17 week, Plug Fest #3





June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair 

IoTivity Release Function Lead


Samsung Electronics Co.,Ltd.

Software R&D Center, IoT Solution Lab. | Web & Convergence Team

Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107

E-mail :juney at samsung.com



From: Agrawal, Sachin [mailto:[email protected]] 
Sent: Wednesday, July 29, 2015 3:24 AM
To: juney at samsung.com; ???
Cc: iotivity-dev at lists.iotivity.org
Subject: RE: Re: [dev] About preparing 0.9.2 Security Release



Hi All,



I created the ?0.9.2-RC2? tag and pushed it to Iotivity repo.



Thanks

Sachin



From: Agrawal, Sachin 
Sent: Tuesday, July 28, 2015 9:36 AM
To: 'juney at samsung.com'; ???
Cc:  <mailto:iotivity-dev at lists.iotivity.org> iotivity-dev at 
lists.iotivity.org
Subject: RE: Re: [dev] About preparing 0.9.2 Security Release



Since all the existing tags have upper-case letters ?RC?, I assume June meant 
to tag it with ?0.9.2-RC2?. 

Am I right?



Thanks

Sachin



From: ??? [ <mailto:juney at samsung.com> mailto:[email protected]] 
Sent: Tuesday, July 28, 2015 8:01 AM
To: ???; Agrawal, Sachin; ???
Cc:  <mailto:iotivity-dev at lists.iotivity.org> iotivity-dev at 
lists.iotivity.org
Subject: Re: Re: [dev] About preparing 0.9.2 Security Release



Hi Sachin



What is the progress?

As soon as the review is completed, please tag "0.9.2-rc2".

Sent from Mobiledesk



---?? ???---
??? : ???(June Yong Young)
???? : 2015/07/28 15:31 (GMT+09:00)
?? : Re: [dev] About preparing 0.9.2 Security Release

Hi Sachi,



When will the review be finished? Everybody is waiting for the completion by 
today.



Regards

June



June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair 

IoTivity Release Function Lead


Samsung Electronics Co.,Ltd.

Software R&D Center, IoT Solution Lab. | Web & Convergence Team

Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107

E-mail :juney at samsung.com



From: Agrawal, Sachin [ <mailto:sachin.agrawal at intel.com> 
mailto:[email protected]] 
Sent: Tuesday, July 28, 2015 2:52 AM
To:  <mailto:juney at samsung.com> juney at samsung.com; ???
Cc:  <mailto:iotivity-dev at lists.iotivity.org> iotivity-dev at 
lists.iotivity.org
Subject: RE: About preparing 0.9.2 Security Release



Hi June,



SRM/Provisioning Mgr API is unable to discover the secure port of the new 
device.

Jira ticket:  <https://jira.iotivity.org/browse/IOT-626> 
https://jira.iotivity.org/browse/IOT-626



It is SpecA mandatory as Provisioning Tool is dependent on this.



Code change is currently under review and will be pushed in 0.9.2-dev as soon 
as it finishes review process.



Thanks

Sachin

From: ??? [ <mailto:juney at samsung.com> mailto:[email protected]] 
Sent: Monday, July 27, 2015 9:12 AM
To: ???; Agrawal, Sachin;  <mailto:iotivity-dev at lists.iotivity.org> 
iotivity-dev at lists.iotivity.org
Cc: Kesavan, Vijay S; Heldt-Sheller, Nathan; ???; ???; ???; ???; ???; ???; ???; 
??
Subject: Re: About preparing 0.9.2 Security Release



Hi Sachin, WooCheol,



Please share the security issues in iotivity mailing list.

- what is the security issue?

- SpecA mandatory related issue? Or not?

- When will it be fixed?



Regards

June


Sent from Mobiledesk



---?? ???---
??? : ???
???? : 2015/07/27 16:58 (GMT+09:00)
?? : About preparing 0.9.2 Security Release

Hi Sachin,



June (release manager) asked me when the gerrit review #1680 will be 
cherry-picked to 0.9.2-dev for testing and RC2.

We confirmed that provisioning tool is working with  
<https://gerrit.iotivity.org/gerrit/#/c/1680> 
https://gerrit.iotivity.org/gerrit/#/c/1680 but, without 1680, we failed to run 
it. 

If possible, could you please share the plan about this change?

Thank you.



BR, Woochul 










http://www.samsung.net/pt_images/C10/securityimage/MSI_20140516060336843.gif



-------------- next part --------------
An HTML attachment was scrubbed...
URL: 
<http://lists.iotivity.org/pipermail/iotivity-dev/attachments/20150731/90af8b6d/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 24007 bytes
Desc: not available
URL: 
<http://lists.iotivity.org/pipermail/iotivity-dev/attachments/20150731/90af8b6d/attachment.png>

Reply via email to