https://issues.apache.org/jira/browse/AMBARI-21911?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=16158606#comment-16158606
 ] 

Hudson commented on AMBARI-21911:
---------------------------------

FAILURE: Integrated in Jenkins build Ambari-trunk-Commit #8026 (See 
[https://builds.apache.org/job/Ambari-trunk-Commit/8026/])
AMBARI-21911 "Retry" upgrade doesn't work if a server action times out 
(hapylestat: 
[http://git-wip-us.apache.org/repos/asf?p=ambari.git&a=commit&h=2170ce0321b8ea2c772c5dcdce38c4d94bea8175])
* (edit) 
ambari-server/src/test/java/org/apache/ambari/server/actionmanager/TestActionDBAccessorImpl.java
* (edit) 
ambari-server/src/main/java/org/apache/ambari/server/actionmanager/ActionDBAccessorImpl.java


> "Retry" upgrade doesn't work if a server action times out
> ---------------------------------------------------------
>
>                 Key: AMBARI-21911
>                 URL: https://issues.apache.org/jira/browse/AMBARI-21911
>             Project: Ambari
>          Issue Type: Improvement
>          Components: ambari-server
>    Affects Versions: 2.6.0
>            Reporter: Dmytro Grinenko
>            Assignee: Dmytro Grinenko
>            Priority: Critical
>             Fix For: 2.6.0
>
>
>  During testing, upgrade was stuck at "Update Target Stack" server action 
> step. The step "TIMEDOUT" due to slow DB and caused all other upgrade steps 
> to be "ABORTED". Once in this state, the upgrade cannot be retried, despite 
> the "Retry" button being clickable. Also in this state the "Pause Upgrade" 
> button is clickable but doesn't work.



--
This message was sent by Atlassian JIRA
(v6.4.14#64029)

Reply via email to