https://issues.apache.org/jira/browse/AMBARI-25244?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel
 ]

Viraj Jasani updated AMBARI-25244:
----------------------------------
    Fix Version/s: 2.7.4
                   trunk
           Status: Patch Available  (was: In Progress)

> Rolling Upgrade support for rack based hosts
> --------------------------------------------
>
>                 Key: AMBARI-25244
>                 URL: https://issues.apache.org/jira/browse/AMBARI-25244
>             Project: Ambari
>          Issue Type: Improvement
>          Components: ambari-server
>    Affects Versions: trunk, 2.7.4
>            Reporter: Viraj Jasani
>            Assignee: Viraj Jasani
>            Priority: Critical
>              Labels: pull-request-available
>             Fix For: trunk, 2.7.4
>
>          Time Spent: 3h 40m
>  Remaining Estimate: 0h
>
> Ambari managed Rolling Upgrade has batch size concept with which multiple 
> hosts are upgraded in parallel. e.g. slave/client components are restarted on 
> multiple hosts in parallel.
> However, we should provide support for parallel hosts upgrade that exist on 
> single rack. If client provides location of rack to hosts mapping file 
> location as part of cluster-env property, we should read the mapping and 
> proceed with parallel Rolling Restart on multiple hosts on single rack.
> This can significantly improve resiliency and availability as slave/client 
> components that don't belong to single rack won't be restarted in parallel.



--
This message was sent by Atlassian JIRA
(v7.6.3#76005)

Reply via email to