Claus Ibsen updated CAMEL-24602:
--------------------------------
    Component/s: build system

> CI test reporting should include elapsed time (duration) not just module/test 
> counts
> ------------------------------------------------------------------------------------
>
>                 Key: CAMEL-24602
>                 URL: https://issues.apache.org/jira/browse/CAMEL-24602
>             Project: Camel
>          Issue Type: Improvement
>          Components: build system
>            Reporter: Claus Ibsen
>            Assignee: Omar Atie
>            Priority: Major
>             Fix For: 4.23.0
>
>
> Today the CI test reporting only shows the *number of modules* and the 
> *number of tests* executed. It would be very useful if the reporting could 
> also include the *elapsed time* (e.g. in minutes) of the build/test runs.
> Ideally the timing should be reported per module (or grouped) so we can 
> pinpoint which modules take disproportionately long to build/test.
> *Motivation*
> We currently run a lot of CI and put too much stress on the CI 
> infrastructure. Having per-module timing data would let us identify the 
> slowest modules and target them for optimization, helping reduce the overall 
> CI load and turnaround time.
> *Suggested outcome*
> - Report total elapsed build/test time.
> - Ideally break the time down per module (or highlight the top N slowest 
> modules) so hotspots are easy to spot.



--